Three Gorges Dafeng (H8-1+H9+H15+H17)

Located off Dafeng Port, Jiangsu. Three offshore substations. Annual generation ~2.6 TWh.

Project timeline verified milestones only — each date carries its provenance mark

Dashed tick marks today (13 Oct 2026).

Revenue & offtake the regime the project was built under

Offtake regime of the vintage — not a recorded contract
Post-subsidy era — provincial pricing (NDRC notice 2021)

Built after the national subsidy ended. From 2021, newly approved offshore wind projects are priced by the provincial price authority — through competitive allocation where conditions allow — with no central subsidy; the grid company settles the part within the local coal benchmark price. A project approved before 2021 that connected after the 2021 deadline takes the guide price of its connection year. Provincial top-ups (Guangdong, Shandong, Zhejiang and others) exist and are recorded on projects only where a source states them. · ◇

A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2025-12-15

Sources & verification

Rests on 13 sources (1 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[5]
Jiangsu Provincial Development and Reform Commission (江苏省发展和改革委员会)2023-09-25
“苏发改能源发〔2023〕995号 ... 依据《行政许可法》《江苏省企业投资项目核准和备案管理办法》等有关规定,同意建设大丰80万千瓦海上风电项目。(成文日期:2023年9月25日)”
supportsConsentConsent granted
Trade press11
[2]
offshoreWIND.biz2025-12
Press report — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operationTurbinesTotal capacityStatus+1 more
[3]
Global Energy Monitor2026-07-02
supportsoperatorCoordinates
[4]
GEBCO Compilation Group2020
supportsWater depth
[6]
Xinhuanet Jiangsu (新华网江苏频道)2025-03-02
Press report — cited, not quoted; read it at the source link.
supportsConstruction startSite rights
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[8]
扬子晚报 (via 盐城发布)2025-09-16◆ 1713吨巨桩落海 (三峡江苏大丰800兆瓦 完成全部单桩施工)
Copyrighted source — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[9]
扬子晚报 (Yangtse Evening Post)2026-07-20◆ 三峡江苏大丰800兆瓦海上风电项目年度发电量突破10亿千瓦时
Copyrighted source — cited, not quoted; read it at the source link.
supportsCommercial operationTurbinesTotal capacity
[10]
扬子晚报 (via 央视新闻客户端)2025-12-20◆ 我国离岸最远海上风电项目全容量并网 (三峡江苏大丰800兆瓦)
Copyrighted source — cited, not quoted; read it at the source link.
supportsCommercial operationTotal capacity
[11]
Global Energy Monitor2026◆ Jiangsu Dafeng H15 (Three Gorges) Offsho…
supportsConstruction startSite rights
[13]
Global Energy Monitor2026◆ Jiangsu Dafeng H17 (Three Gorges) Offsho…
supportsConstruction startSite rights
[14]
Global Energy Monitor2026◆ Jiangsu Dafeng H9 (Three Gorges) Offshor…
supportsConstruction startSite rights
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacityWater depthCoordinates