Choshi Offshore Wind (R1 withdrawn — re-auction)

Located off Choshi City, Chiba Prefecture, in the Pacific Ocean. Distinct from the Choshi Offshore Demonstration turbine (operational).

Status
On Holdlifecycle stage
FragileHafrok completion outlook
Ownership
—
Location
Japan
Northwest Pacific
Technology
Capacity 403 MW ◇ Turbines 31 × 13 MW ◇ Model GE Haliade X ◇
Foundation —
Site & conditions
Site rights Seabed rights held ∴
Origination Japan Offshore Wind Round 1 (general sea-area public solicitation) · 2021 ·
Water depth 16–20 m ≈ Wind speed 8.4 m/s @ 150 m ≈
Revenue & grid
Offtake Other withdrawn ◇ Grid Not recorded ◇ Connection Tokyo Electric Power (TEPCO) grid (Chiba) ◇
Schedule
FID Not taken
COD · announced 2031 ○
COD · Hafrok —
On hold since 27 Aug 2025 ◆

Delivery outlook modelled by Hafrok · calibrated on delivered projects

—
on hold — no credible date; the chart shows when a restarted project might complete
The developer's last guidance was 2031 · not treated as a schedule while the project is on hold
Chance of delivery
≈14% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. A market with a thinner delivery record, technical complexity and no offtake contract yet pull this one slightly below that. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034 Developer-announced COD: 2031 ANNOUNCED 2031
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈14%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27’28’29’30’31Developer-announced COD: 2031 announced COD 2031Japan Offshore Wind Round 1 (general sea-area public solicitation) — awarded to Mitsubishi-led consortium (Mitsubishi Corp + MC Energy Solutions + Chubu + C-Tech)Japan Offshore Wind Round 1 (general sea-area public solicitation) Dec 2021 · auction recordView the source for On holdOn hold 27 Aug 2025 ◆Japan Offshore Wind Round 1 (general sea-area public solicitation) — awarded to Mitsubishi-led consortium (Mitsubishi Corp + MC Energy Solutions + Chubu + C-Tech) 2021-12 ORIGINATIONTODAYMitsubishi-led consortium (Mitsubishi Corp + MC Energy Solutions + Chubu + C-Tech) Mitsubishi-led consorti… Mitsubishi-led consorti… exited 2021-12Japan Offshore Wind Round 1 (general sea-area public solicitation) — awarded to Mitsubishi-led consortium (Mitsubishi Corp + MC Energy Solutions + Chubu + C-Tech)
Dashed tick marks today (13 Oct 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open

Tender award · Japan Offshore Wind Round 1 (general sea-area public solicitation) awarded 2021-12, withdrawn 2025-09. No live offtake on record. ◇

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Japan Round 1 re-auction (Noshiro-Mitane-Oga, Yurihonjo, Choshi) ◇
expected 2026 · planned · the round’s published documents do not name this project
The three sites a Mitsubishi-led consortium WON in Round 1 (2021) and WITHDREW from in Aug 2025 are to be re-auctioned "as early as 2026", expected before Round 4; timing not firmly fixed.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation not started
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operation2031

Sources & verification

Rests on 10 sources (1 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[6]
Chiba Prefectural Government (Environmental Policy Division)2026-08-21◆ (仮称)銚子市沖洋上風力発電事業(法対象事業)〔事業者:東京電力リニューアブルパ…
“東京電力リニューアブルパワー株式会社 (仮称)銚子市沖洋上風力発電事業 / 銚子市沖(約4,000ヘクタール) / 設置する発電所の出力:最大420,000キロワット(単機出力15,000キロワットから20,000キロワット、最大27基) / 送付:令和8年8月20日 公告:令和8年8月21日 縦覧期間:令和8年8月21日から令和8年9月25日まで (English: Tokyo Electric…”
supportsStatus note
Auction results1
[9]
Aquilo Energy / EEAS2026-06-22◆ jp-round1-2021-jp-tenders-study
Japanese offshore-wind tenders study: 30-yr occupancy permit, scheduled operation <=8 years after Occupancy Plan certification
supportsOfftake history
Auction pipeline1
[10]
Shulman Advisory2026
Japan to re-auction the three Round-1 sites (Noshiro-Mitane-Oga, Yurihonjo, Choshi) dropped by Mitsubishi, as early as 2026 with a revised price-floor/ceiling framework.
supportsJapan Round 1 re-auction (Noshiro-Mitane-Oga, Yurihonjo, Choshi)
Trade press6
[2]
DeepWind2025
supportsTotal capacityMechanismDetailStatusConnection point
[3]
GEM2026
supportsTurbinesModelUnit capacityTotal capacityCoordinates
[4]
GEBCO Compilation Group2020
supportsWater depth
[5]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[7]
offshoreWIND.biz2026-08-26◆ TEPCO Starts EIA Process for New Choshi …
Press report — cited, not quoted; read it at the source link.
supportsStatus note
[8]
offshoreWIND.biz2025-08-27◆ Mitsubishi Decides to Exit Three Offshor…
Press report — cited, not quoted; read it at the source link.
supportsOn hold
Unverified import1
[1]
unknown
supportsConsentCommercial operationTotal capacityWater depthCoordinates