Deutsche Bucht

Located 95 km northwest of the island of Borkum in the German North Sea EEZ, at 38–42 m water depth.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted Feb 2010 ◆View the source for Final investment decisionFinal investment decision 18 Aug 2017 ◆View the source for Offshore constructionOffshore construction Sep 2018 ◆View the source for First powerFirst power Jul 2019 ◆View the source for Commercial operationCommercial operation 31 Mar 2020 ◆No origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDHighland Group Holdings → Northland Power — 100.0% · closed 2017-08 2017-03 ACQUISITIONTODAYHighland Group Holdings Highland Group Holdings Highland Group Holdings exited 2017-03Northland Power — 100% today · operator Northland Power Northland Power 100%Highland Group Holdings → Northland Power — 100.0% · closed 2017-08 100%
Dashed tick marks today (13 Oct 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2019→2020-Q1→2020-03-31→2019-10 · 4 recorded revisions · held within the year (first announced 2019, latest 2019-10)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2020-03-31
Offshore construction2018-09 → 2020-03-31
Construction ports
PortCuxhaven (Cuxport Terminal) ◆·foundations · quay 734 m · crane 650 t · draft 12.7 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationDeutsche Bucht offshore substation·33/155 kV · in service 2019 · owner Northland Power (wind farm owner) — farm-owned, not TSO-owned
HVDC systemBorWin2·800 MW · ±300 kV · in service 2015-01 · shared with Albatros, Veja Mate
Converter supplierSiemens (HVDC PLUS); Prysmian cables·BorWin2 · Nordic Yards, Warnemünde, Germany · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20132014201520162017201820192020202120222023202420252026developer’s stated start 2020-Q1nowBorWin2BorWin2first planned 2013first planned 2013in service 2015-01in service 2015-01Deutsche Bucht offshore substationDeutsche Bucht offshore substationin service 2019in service 2019

Sources & verification

Rests on 14 sources (11 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[9]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2010-02◆ Genehmigungsbescheid Offshore-Windpark D…
“Auf den Antrag der Eolic Power GmbH ... werden Errichtung und Betrieb von 42 Windenergieanlagen (WEA) einschließlich Nebenanlagen im Bereich der deutschen ausschließlichen Wirtschaftszone (AWZ) in der…”
supportsConsentConsent granted
[13]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Deutsche Bucht": 31 units, 260.4 MW gross, statuses {'In Betrieb': 31}, operators ['Northland Deutsche Bucht GmbH'], commissioned 2019-07-26..2019-09-25, planned None..None.”
supportsRegister entry
Operator7
[1]
Northland Power2025
“31x MHI Vestas 8.4 MW turbines ... 100% owner of the €1.5 billion Deutsche Bucht offshore wind farm ... completed in March 2020 ... 95 km west of Borkum in the German Exclusive Economic Zone ... 39-41…”
supportsUnit capacityWater depthDistance from shore
[2]
Northland Power2017-08-18◆ Northland Power's Deutsche Bucht Offshor…
“TORONTO, ON --(Marketwired - August 18, 2017) - Northland Power Inc. [...] today announced that the EUR1.3 billion Deutsche Bucht (" DeBu ") project has reached financial close, with all of the equity…”
supportsFinal investment decisionMechanismDetail
[3]
Northland Power2017-08-17◆ Northland Power Completes Acquisition of…
“TORONTO, ON --(Marketwired - August 17, 2017) - Pursuant to the agreement to purchase that was announced on March 3, 2017, Northland Power Inc. [...] today announced that it has completed the acquisit…”
supportsoperator
[4]
Northland Power2020-04-01◆ Northland Power's Deutsche Bucht Offshor…
“TORONTO, March 31, 2020 (GLOBE NEWSWIRE) -- Northland Power Inc. [...] confirmed today that its 252 megawatt (MW) Deutsche Bucht offshore wind project achieved full completion on March 31, 2020. All 3…”
supportsCommercial operationFoundation
[5]
Northland Power2018
“two additional pilot wind turbines ... an additional 17 MW of capacity to the base 252 MW project for a total of 269 MW ... two turbines using Mono Bucket foundations ... a new type of foundation stru…”
supportsTotal capacity
[14]
Bundesanzeiger2021-12-31◆ Northland Deutsche Bucht GmbH, Oststeinb…
“Die DBU vermarktet seit Juli 2019 den produzierten Strom durch Direktvermarktung nach dem Erneuerbare-Energien-Gesetz (EEG). Die Direktvermarktung erfolgt seit 2018 über den Dienstleister Vattenfall E…”
supportsCOD historyMechanismDetail
[15]
Unternehmensregister2026-01-26◆ Northland Deutsche Bucht GmbH, Rendsburg…
“Die Gesellschaft wird im Handelsregister des Amtsgerichts Lübeck unter der Nummer HRB 19589 HL geführt. ... Die NDBG vermarktet seit Juli 2019 den produzierten Strom durch Direktvermarktung nach dem E…”
supportsMechanismDetail
OEM1
[6]
Vestas / MHI Vestas Offshore Wind2018-07-20◆ Financial Close for Industry First Demo …
“the first offshore wind farm worldwide to test the Mono Bucket foundation structure under commercial operating conditions ... V164-8.4 MW turbines ... two turbines ... 17 MW of capacity ... financial …”
supportsModelUnit capacity
Trade press4
[7]
Offshore Wind Biz2019-07-29◆ Deutsche Bucht Delivers First Power | Of…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
NS Energy2020
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionSite rightsTurbinesModelUnit capacity+4 more
[10]
Offshore Wind Biz2019-01-08
Press report — cited, not quoted; read it at the source link.
supportsfoundations
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed