Vesterhav Nord & Syd

Vesterhav Nord (176 MW, 21 turbines) off Harboore/Thyboron + Vesterhav Syd (168 MW, 20 turbines) off Ringkobing.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2017’18’19’20’21’22’23’24’25’26Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/SVesterhav Nord & Syd (Danish near-shore tender) Sep 2016 · auction recordView the source for Consent grantedConsent granted Dec 2020 ◆View the source for Final investment decisionFinal investment decision Dec 2021 ◆View the source for Offshore constructionOffshore construction Feb 2023 ◆View the source for First powerFirst power Nov 2023 ◆View the sources for Commercial operationCommercial operation Mar 2024 ◆Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/S 2016-09 ORIGINATIONVattenfall → Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) — stake not disclosed · closed 2023-07 2023-Q2 FARMDOWNTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYVattenfall — 92% today · operator Vattenfall Vattenfall 92%Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) Local residents and hol… Local residents and hol… exited 2023-Q2Community shareholders — 8% today · community Community shareholders Community shareholders 8%Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/S Vattenfall → Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) — stake not disclosed · closed 2023-07 Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2020→2020→2020→2023→2024-Q1→2024-03 · 6 recorded revisions · slipped +3.7 yr (first announced 2020)

Revenue & offtake contract duration and price levels · money of the day

350 MW contracted — tender award
● Tender award · Vesterhav Nord & Syd (Danish near-shore tender)
Price47.5 DKK_ore/kWh ·Capacity350 MWAwardedSep 2016

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2024-03
Offshore construction2023-02 → 2024-03
Construction ports
PortPort of Thyboron ◆foundation marshalling
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 0
Offshore substationNone by design·nearshore direct-to-shore design; turbine cables run to onshore coastal collection stations (Nord: Klinkby, then Idomlund; Syd: near the coast, then Stovstrup) — Energinet

Sources & verification

Rests on 13 sources (15 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator7
[1]
Vattenfall2024-09-12◆ Danish offshore wind farms Vesterhav Nor…
“Danish offshore wind farms Vesterhav Nord and Vesterhav Syd inaugurated … combined installed capacity of 344 MW … 1.5 TWh fossil-free electricity … 5.5 to 10 kilometres … service facility at Hvide San…”
supportsCommercial operationTotal capacityDistance from shore
[2]
Vattenfall2021-12-15◆ Vattenfall gives go-ahead for Vesterhav …
“With the final investment decision at a value of 769 MEUR, Vattenfall and its suppliers initiated the last stage of the development of the two offshore wind farms ... combined installed capacity of 34…”
supportsFinal investment decisionTurbinesUnit capacity
[4]
Vattenfall2023-11-10◆ Vattenfall supplies first power from Den…
“On 10 November, the first power from Vattenfall's offshore wind farm Vesterhav Syd was supplied to the Danish power grid.”
supportsFirst power
[5]
Vattenfall2024-01-09◆ Vattenfall connects Danish offshore wind…
“Every single turbine at the offshore windfarm Vesterhav Syd has now supplied the first power and the offshore wind farm is now completely connected to the Danish power grid - initial power delivery oc…”
supportsCommercial operationStatusConnection point
[8]
Vattenfall2024◆ Power plants: Vesterhav Nord - Vattenfal…
“Vattenfall ownership share 92% … between 5.5 and 8.4 kilometres from Thyborøn and Ferring Sø on the Jutland coast … 21 units … 176 MWe.”
supportsoperatorcommunityTotal capacity
[11]
Vattenfall2016-09-12◆ Vattenfall wins Danish Near Shore Wind  …
“Vattenfall has won the Danish Near Shore Wind Tender (DNS) … the outcome of the tender is based on Vattenfall delivering the lowest bid of 0,475 kr/kWh … Vattenfall will now develop two wind farms wit…”
supportsMechanismStrike / priceDetail
[15]
Vattenfall2023-03-31
“Vattenfall afslutter fundamenter til Vesterhav Syd – nu begynder arbejdet i nord ... Siden den 20. februar har installationsskibet "DEME Innovation" nedrammet 20 monopæle i Vesterhav Syd havmøllepark …”
supportsOffshore construction
OEM1
[3]
Siemens Gamesa Renewable Energy2021-12-15◆ Delivering in Denmark: Siemens Gamesa re…
“41 SG 8.0-167 Direct Drive offshore wind turbines … Vesterhav Nord: 21 SG 8.0-167 DD offshore wind turbines … Vesterhav Syd: 20 SG 8.0-167 DD offshore wind turbines … A three-year Service agreement, w…”
supportsTurbinesModelUnit capacityFoundation
Auction results1
[23]
AURES II / DTU2026-06-22◆ dk-vesterhav-near-shore-aures
AURES II Denmark case study: two-sided sliding-premium CfD vs day-ahead spot, FLH cap, DKK 100m guarantee, support-volume clawback
supportsTender award · Vesterhav Nord & Syd (Danish near-shore tender)
Trade press4
[7]
Offshore Wind Biz2024-09-12
Press report — cited, not quoted; read it at the source link.
supportsConsentTurbinesUnit capacityTotal capacityStatus+2 more
[10]
Thyboron Port2023
“Thyboron Port was selected as the marshalling base for installing 41 foundations supporting 8.4 MW Siemens Gamesa offshore wind turbines … 41 monopiles (77 m long, ~622 tonnes each) … proximity to the…”
supportsFoundationWater depthfoundation marshalling
[14]
offshoreWIND.biz2024-03-12◆ Vattenfall Links Vesterhav Nord to Danis…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD history
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed