Hollandse Kust Zuid

Located 18-35km off coast between The Hague and Zandvoort. 235.8 km2 site area.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2017’18’19’20’21’22’23’24’25’26View the sources for Consent appliedConsent applied 19 Aug 2016 ◆View the sources for Consent grantedConsent granted 8 Dec 2016 ◆Hollandse Kust (zuid) Sites I & II — awarded to VattenfallHollandse Kust (zuid) Sites I & II Mar 2018 · auction recordView the source for Final investment decisionFinal investment decision 2020 ◆View the source for Onshore constructionOnshore construction 2021 ◆View the source for First powerFirst power 2022-Q3 ◆View the sources for Commercial operationCommercial operation 2024 ◆Hollandse Kust (zuid) Sites I & II — awarded to Vattenfall 2018-03 ORIGINATIONVattenfall → BASF — 49.5% · €1,600m · closed 2021-09 2021-06 FARMDOWNBASF → Allianz Capital Partners — 25.2% · closed 2022-Q1 2021-12 TODAYVattenfall — 50.5% today · operator Vattenfall Vattenfall 50.5%BASF — 24.3% today BASF BASF 24.3%Allianz — 25.2% today Allianz Allianz 25.2%Hollandse Kust (zuid) Sites I & II — awarded to Vattenfall Vattenfall → BASF — 49.5% · €1,600m · closed 2021-09 49.5%BASF → Allianz Capital Partners — 25.2% · closed 2022-Q1 25.2%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023→2024 · 2 recorded revisions · slipped +1.0 yr (first announced 2023)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2024
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationHollandse Kust (zuid) Alpha·66/220 kV · in service 2022 · owner TenneT (Dutch TSO)
Offshore substationHollandse Kust (zuid) Beta·66/220 kV · in service 2022 · owner TenneT (Dutch TSO)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20222023202420252026developer’s stated start 2024nowHollandse Kust (zuid) AlphaHollandse Kust (zuid) Alphain service 2022in service 2022Hollandse Kust (zuid) BetaHollandse Kust (zuid) Betain service 2022in service 2022

Sources & verification

Rests on 14 sources (16 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[7]
Netherlands Enterprise Agency (RVO)2018-10◆ Hollandse Kust (zuid) III & IV Project a…
supportsFoundationMean wind speedWater depthDistance from shoreCoordinates
[14]
RVO — Bureau Energieprojecten (energietransitie.nl)2026-08-23◆ Dutch Bureau Energieprojecten register (…
“Listing row "Net op zee - Hollandse Kust (zuid)" (key net-op-zee-hollandse-kust-zuid); offshore docket page text hash bde22aa66f995d18… (6139 chars).”
supportsRegister entry
Operator8
[1]
Vattenfall◆ Power plants: Hollandse Kust Zuid - Vatt…
“Electricity Capacity: 1,509 MWe. Turbines: 139.”
supportsTurbinesTotal capacityMechanismDetailStatus+1 more
[4]
Vattenfall2023-09-29◆ Offshore wind farm Hollandse Kust Zuid i…
“Dutch King Willem-Alexander officially inaugurated wind farm Hollandse Kust Zuid (29 September 2023). The wind farm is expected to be fully operational in 2024.”
supportsCOD history
[5]
Vattenfall2023-06-19◆ The last turbine for Hollandse Kust Zuid…
“Almost two years after construction of Hollandse Kust Zuid began, the last turbine of the offshore wind farm has been installed.”
supportsOnshore construction
[9]
Vattenfall2023
supportsoperatorowner
[10]
Vattenfall
“Het windpark is in september 2023 geopend door koning Willem-Alexander ... In bedrijf: september 2023”
supportsCommercial operation
[11]
Ministerie van Economische Zaken (Staatscourant)2016-12-08
“Kavelbesluit I windenergiegebied Hollandse Kust (zuid) ... 's-Gravenhage, 8 december 2016 ... De Minister van Economische Zaken, H.G.J. Kamp”
supportsConsentConsent appliedConsent granted
[13]
Vattenfall2021-04-29◆ Vattenfall — 210429 q1 transcript
“And we mentioned one of them, today, a 15 year one with Air Liquide in relation to Hollandse Kust Zuid”
supportsMechanismDetail
[20]
Staatscourant (Koninkrijk der Nederlanden)2016-08-18◆ Staatscourant 2016-43343: Kennisgeving o…
“Van vrijdag 19 augustus 2016 tot en met donderdag 29 september 2016 liggen de ontwerpkavelbesluiten ter inzage voor de kavels I en II”
supportsConsentConsent appliedConsent granted
OEM1
[2]
Siemens Gamesa2019-11-27◆ Vattenfall’s Hollandse Kust Zuid 1&2 win…
“The newest version of Siemens Gamesa offshore wind turbine - launched just a day ago - can reach 11 MW capacity under specific site conditions and it is the perfect fit for the world's first subsidy-f…”
supportsModelUnit capacity
Trade press3
[6]
offshoreWIND.biz2022-08-02
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
NS Energy2020-06-05
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[12]
Seaway72026-07-20◆ Hollandse Kust Zuid Offshore Wind Farm -…
“Hollandse Kust Zuid ... fully operational since 2024”
supportsCommercial operation