Five Estuaries

Split across two seabed areas covering 128km². Grid connection at East Anglia Connection Node near Lawford, Essex.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
Location
United Kingdom
North Sea
Technology
Capacity 1,080 MW ◆
Turbines —
Foundation —
Site & conditions
Site rights Seabed rights held ∴
Origination The Crown Estate 2017 Offshore Wind Extensions opportunity · 2020 ·
Water depth 37–51 m ≈ Wind speed 9.9 m/s @ 150 m ≈
Revenue & grid
Offtake CfD ◆ Grid Applied ◆ Connection Five Estuaries 220/66 kV Offshore Substation — NESO TEC … ◆
Schedule
FID Not taken
COD · announced 2030 ◆
COD · Hafrok 2032 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2032
expected year of commercial operation
The developer says 2030; Hafrok expects 2032 — 2 years later.
Chance of delivery
≈80% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; its size and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2031: 14.2% (conditional on completion) 2032: 30.5% (conditional on completion) 2033: 24.0% (conditional on completion) 2034: 14.4% (conditional on completion) 2035: 8.0% (conditional on completion) 2036: 4.4% (conditional on completion) 2037: 2.4% (conditional on completion) 2038: 1.3% (conditional on completion) 2039: 0.8% (conditional on completion)2026now20282030203230%EXPECTED203420362038 Developer-announced COD: 2030 ANNOUNCED 2030
COD probability by year, conditional on completion
YearProbability
203114.2%
2032 (expected)30.5%
203324.0%
203414.4%
20358.0%
20364.4%
20372.4%
20381.3%
20390.8%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2025. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2029 Q2; the faster quarter of similar projects would be done by 2027 Q3, the slower quarter not until 2030 Q3.
3
Still needs an offtake award: UK-CFD-AR8
The project has no offtake contract yet. The next visible auction is around 2026 Q4; winners typically reach final investment decision about 2 years after an award (2028 Q4), then build time on top gives 2032 Q1. That is later than the milestone timing, so the auction sets the date.
4
Result
Expected commercial operation 2032, likely range 2031–2033 (the middle half of outcomes for similar projects). The developer's announced date (2030) is earlier than similar projects have managed — Hafrok's own date is used and the difference is flagged above.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈80%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2021’22’23’24’25’26’27’28’29’30’31’32Developer-announced COD: 2030 announced COD 2030The Crown Estate 2017 Offshore Wind Extensions opportunity — awarded to incumbent operators of the seven parent farmsThe Crown Estate 2017 Offshore Wind Extensions opportunity Sep 2020 · auction recordView the source for Consent appliedConsent applied 25 Mar 2024 ◆View the sources for Consent grantedConsent granted 17 Dec 2025 ◆Commercial operation 2032 ·Hafrok expectedThe Crown Estate 2017 Offshore Wind Extensions opportunity — awarded to incumbent operators of the seven parent farms 2020-09 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDMacquarie Asset Management → Copenhagen Infrastructure Partners (CI V) — 25% · closed 2026-10 2026-10-13 ACQUISITIONRWE → EDF power solutions UK and Ireland — 33.33% 2026-10-08 ACQUISITIONTODAYRWE RWE RWE exited 2026-10-08Siemens Financial Services Siemens Financial Servi… Siemens Financial Servi… exited 2020-09ESB — 20.83% today ESB ESB 20.83%Sumitomo Corporation — 20.83% today Sumitomo Corporation Sumitomo Corporation 20.83%Green Investment Group (Macquarie) Green Investment Group Green Investment Group exited 2020-09Macquarie Asset Management Macquarie Asset Managem… Macquarie Asset Managem… exited 2026-10-13Copenhagen Infrastructure Partners (CI V) — 25% today CIP CIP 25%EDF power solutions UK and Ireland — 33.33% today · operator EDF power solutions UK … EDF power solutions UK … 33.33%The Crown Estate 2017 Offshore Wind Extensions opportunity — awarded to incumbent operators of the seven parent farms Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Macquarie Asset Management → Copenhagen Infrastructure Partners (CI V) — 25% · closed 2026-10 25%RWE → EDF power solutions UK and Ireland — 33.33% 33.33%
Dashed tick marks today (13 Oct 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
CfD allocation round
The UK's principal route — a 15-year, CPI-indexed, two-sided CfD awarded in annual competitive rounds.
Next visible round · from the auction calendar
CfD Allocation Round 8 ◇
expected H2 2026 · scheduled · the round’s published documents do not name this project
AR8 confirmed (gov update, Mar 2026) to OPEN July 2026 — brought forward from the earlier mid/late-2026 expectation
Corporate PPA
Bilateral long-term offtake with corporate buyers; can cover part of output alongside or ahead of a CfD.
Merchant
Uncontracted sale into the wholesale market — no price floor, full exposure to power prices.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation not started
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2030

Sources & verification

Rests on 16 sources (10 primary) · ◆ 10 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator5
[5]
UK Legislation (Secretary of State for Energy Security and Net Zero)2025-12-17◆ The Five Estuaries Offshore Wind Farm Or…
“The Five Estuaries Offshore Wind Farm Order 2025 — Date made: 17th December 2025.”
supportsConsentConsent granted
[12]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 9803: Site Name "Five Estuaries - Wind Farm", Development Status "Application Submitted", Installed Capacity 300 MWelec, Operator "RWE Renewables"”
supportsRegister entry
[14]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 9803: Site Name "Five Estuaries - Wind Farm", Development Status "Planning Permission Granted", Installed Capacity 1080 MWelec, Operator "RWE Renewables", Recor…”
supportsRegister entry
[15]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010115: "Five Estuaries Offshore Wind Farm"; applicant "Five Estuaries Offshore Wind Farm Ltd"; Stage "Post-decision"; anticipated submission between January and March 2024; applie…”
supportsConsentConsent appliedConsent granted
[17]
Copenhagen Infrastructure Partners2026-10-13◆ Copenhagen Infrastructure Partners acqui…
“Copenhagen Infrastructure Partners (CIP), through its fifth flagship fund, Copenhagen Infrastructure V (CI V), has acquired the 25% share previously held by the Macquarie-led consortium in the Five Es…”
supportsowner
Operator5
[3]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Five Estuaries Offshore Wind Farm,FIVE ESTUARIES OFFSHORE WIND FARM LIMITED,Five Estuaries 220/66 kV Offshore Substation,,0,1080,1080,31/10/2030,Scoping,Direct Connection,NGET,Wind Offshore,a1f4L00000…”
supportsCommercial operationStatusConnection point
[4]
RWE UK2025-12-18◆ Secretary of State grants planning conse…
“The project is owned by RWE (33.33%), a Macquarie-led consortium (25%), ESB (20.83%) and Sumitomo Corporation (20.83%). The project will seek a route to market ahead of financial decision and start of…”
supportsowner
[6]
Sumitomo Corporation Europe2025-12-17
“obtained a Development Consent Order from the UK Secretary of State for Energy Security and Net Zero ... A potential maximum installed generation capacity of the Project is 1080MW ... power generation…”
supportsTotal capacityMechanism
[13]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000450: "Five Estuaries Offshore Wind Farm", Status "Scoping", MW Connected 0, Effective From 2030-10-31, Customer "FIVE ESTUARIES OFFSHORE WIND FARM LIMI…”
supportsRegister entry
[16]
RWE2026-10-08◆ Rwe completes sale of shares in five est…
“RWE has today confirmed completion of the divestment of its 33.33% share in Five Estuaries Offshore Wind Farm to fellow power generator EDF. As a result of the sale, EDF will take over responsibility …”
supportsoperator
Auction pipeline1
[18]
DESNZ (gov.uk)2026◆ govuk-cfd-ar8
gov.uk AR8 collection — Allocation Framework, statutory framework and CIB documents published ahead of the round.
supportsCfD Allocation Round 8
Trade press4
[7]
offshoreWIND.biz2025-12
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[9]
The Crown Estate (open data, ArcGIS)2026-04-17
supportsCoordinates
[10]
GEBCO Compilation Group2020
supportsWater depth
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTotal capacity