Nakwol

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2028
expected year of commercial operation
Chance of delivery
≈96% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A market with a thinner delivery record, technical complexity and no offtake contract yet pull this one slightly below that.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2027: 12.6% (conditional on completion) 2028: 46.8% (conditional on completion) 2029: 28.2% (conditional on completion) 2030: 9.3% (conditional on completion) 2031: 2.5% (conditional on completion) 2032: 0.7% (conditional on completion)2026now2027202847%EXPECTED2029203020312032
COD probability by year, conditional on completion
YearProbability
202712.6%
2028 (expected)46.8%
202928.2%
20309.3%
20312.5%
20320.7%
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2025. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2027 Q3; the faster quarter of similar projects would be done by 2026 Q3, the slower quarter not until 2028 Q1.
3
Result
Expected commercial operation 2028, likely range 2027–2028 (the middle half of outcomes for similar projects). The typical build time from the construction start is used.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈96%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

Dashed tick marks today (13 Oct 2026).

Revenue & offtake contract duration and price levels · money of the day

365 MW contracted — utility PPA
● Utility PPA · South Korea 2023 Wind Fixed-Price Auction — offshore carve-out
Priceprice undisclosed ·Capacity364.8 MWAwardedDec 2023
Term20 yrs

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation under way
Installation · on record
StageUnder Construction
Offshore constructionstarted 2025-05-05
Turbinesnot reportedshown when the developer reports a dated count
Expected start of operationnot stated

Sources & verification

Rests on 11 sources (1 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[10]
Yeonggwang County (영광군)2021-04-01◆ 영광군 고시 제2021-32호 공유수면 점·사용 허가 고시 (영광 낙월 …
“1. 허가번호 : 영광군 제2021 - 03호2. 허가년월일 : 2021년 3월 31일3. 점․사용의 목적 : 영광 낙월 해상풍력발전단지 건설공사 및 운영4. 점․사용의 장소 : 영광군 낙월면 안마도 해상 일원”
supportsConsentConsent granted
Auction results1
[11]
Shin and Kim2026-06-22◆ kr-rps-wind-2023-kr-rps-terms
Korea RPS fixed-price offshore: completion-period bands 60/72/78 months; REC-price cut / cancellation on miss
supportsUtility PPA · South Korea 2023 Wind Fixed-Price Auction — offshore carve-out
Trade press9
[1]
Global Energy Monitor2025
supportsFinal investment decisionOnshore constructionOffshore constructionSite rightsTotal capacity
[2]
Global Energy Monitor2026
supportsCoordinates
[3]
4C Offshore2025
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityFoundation
[4]
GEBCO Compilation Group2020
supportsWater depth
[5]
Kaohoon International2025-10-17
“B.Grimm Power Korea directly holds 49% of the issued shares in Nakwol 1. [after acquiring an additional 20.8% from Myungwoon Industry Development and selling its 29% holding in Myungwoon back to that …”
supportsdeveloperowner
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[7]
전기신문 (Electimes)2025-12-10
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
헤럴드경제 미주판 (Herald Economy, US edition)2026-06-11◆ 낙월해상풍력, 13개월만에 모노파일 64기 시공 완료
Copyrighted source — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionSite rights
[9]
아시아경제 (Asia Economy)2025-12-10◆ 낙월해상풍력 첫 상업운전 — 2024년 3월 착공 이후 21개월 만
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionSite rights