Global Tech I

140 km from its logistics base in Emden; at its 2015 inauguration the most distant wind farm from the German coast.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2006’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted May 2006 ◆View the source for Final investment decisionFinal investment decision Jul 2011 ◆View the source for Onshore constructionOnshore construction 2012 ◆View the source for Offshore constructionOffshore construction Sep 2012 ◆View the sources for First powerFirst power Sep 2014 ◆View the sources for Commercial operationCommercial operation Sep 2015 ◆Windreich AG, Norderland Projekt, Stadtwerke München, HSE (ENTEGA), EGL (Axpo), Esportes Offshore, FC Windenergy, GTU I GmbH — stake not disclosed · closed 2013-06 2012-01 JV FORMATIONNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDSeven minority shareholders → Globaleye Capital AG — 26.0% · closed 2022-12 2022-11 Transfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYWindreich AG Windreich AG Windreich AG exited 2012-01Norderland Projekt Norderland Projekt Norderland Projekt exited 2012-01Stadtwerke München — 24.9% today · co-owner Stadtwerke München Stadtwerke München 24.9%HSE (ENTEGA) HSE HSE exited 2012-01EGL (Axpo) EGL EGL exited 2012-01Esportes Offshore Esportes Offshore Esportes Offshore exited 2012-01FC Windenergy FC Windenergy FC Windenergy exited 2012-01GTU I GmbH GTU I GmbH GTU I GmbH exited 2012-01Seven minority shareholders Seven minority sharehol… Seven minority sharehol… exited 2022-11Globaleye Capital AG — 26% today · co-owner Globaleye Capital AG Globaleye Capital AG 26%Entega — 24.9% today · co-owner Entega Entega 24.9%Axpo International — 24.1% today · co-owner Axpo International Axpo International 24.1%Windreich AG, Norderland Projekt, Stadtwerke München, HSE (ENTEGA), EGL (Axpo), Esportes Offshore, FC Windenergy, GTU I GmbH — stake not disclosed · closed 2013-06 Seven minority shareholders → Globaleye Capital AG — 26.0% · closed 2022-12 26%
Dashed tick marks today (13 Oct 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2015-Q3→2015-09 · 2 recorded revisions · held within the year (first announced 2015-Q3, latest 2015-09)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2015-09
Offshore construction2012-09 → 2015-09
Construction ports
PortBremerhaven ◆·assembly and staging · quay 4930 m · draft 12.8 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationGlobal Tech I Umspannplattform (combined transformer and accommodation platform)·155/33 kV · in service 2013 · owner Global Tech I Offshore Wind GmbH (wind farm owner; farm-owned platform)
HVDC systemBorWin3·900 MW · ±320 kV · in service 2019-08 · shared with EnBW Hohe See
Converter supplierSiemens (HVDC PLUS); Petrofac EPCI·BorWin3 · Drydocks World, Dubai, UAE · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20132014201520162017201820192020202120222023202420252026developer’s stated start 2015-Q3nowBorWin3BorWin3first planned 2019first planned 2019in service 2019-08in service 2019-08Global Tech I Umspannplattform (combined transformer and accommodation platform)Global Tech I Umspannplattform (c…in service 2013in service 2013

Sources & verification

Rests on 14 sources (10 primary) · ◆ 11 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2006-05◆ Genehmigungsbescheid Offshore-Windpark G…
“Hamburg, den 24.05.2006 Genehmigungsbescheid Auf den Antrag der Firma Nordsee Windpower GmbH [...] Hindenburgufer 247, 24106 Kiel, genehmigt. 1. Gegenstand dieser Genehmigung sind 80 (achtzig) WEA [..…”
supportsConsentTurbinesWater depthConsent granted
[12]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Global Tech I": 80 units, 400.0 MW gross, statuses {'In Betrieb': 80}, operators ['Global Tech I Offshore Wind GmbH'], commissioned 2014-09-06..2015-07-27, planned None..None.”
supportsFirst power
Operator4
[5]
Axpo2015-09-02◆ Swiss offshore wind farm Global Tech I i…
“02.09.2015 - The offshore wind farm Global Tech I (GTI), located in the North Sea 140 kilometres off the German coastline, officially went into operation today. With a capacity of 400 megawatts, it is…”
supportsco-ownerCommercial operationCOD historyTurbinesUnit capacity+2 more
[7]
Global Tech I Offshore Wind GmbH2025◆ Our Story - Global Tech I Offshore Wind …
“Seit 2022 gehört die Globaleye Capital AG zum Kreis der Gesellschafter von Global Tech I. [...] Jede einzelne Tripode besteht aus rund 900 Tonnen Stahl, ist 60 Meter hoch und wird in Wassertiefen von …”
supportsco-ownerFirst powerFoundationMechanismDetail
[16]
Unternehmensregister2024-01-15◆ Global Tech I Offshore Wind GmbH, Hambur…
“Die Gesellschaft "Global Tech I Offshore Wind GmbH" hat ihren Sitz in 20459 Hamburg, Rödingsmarkt 39, und ist unter HR B Nr. 117586 im Handelsregister des Amtsgerichts Hamburg eingetragen. [...] Ferne…”
supportsMechanismDetail
[17]
Unternehmensregister2025-11-04◆ Global Tech I Offshore Wind GmbH, Hambur…
“Die Gesellschaft "Global Tech I Offshore Wind GmbH" hat ihren Sitz in 20459 Hamburg, Rödingsmarkt 39, und ist unter HR B Nr. 117586 im Handelsregister des Amtsgerichts Hamburg eingetragen. [...] GT I …”
supportsMechanismDetail
Financier1
[2]
European Investment Bank (EIB)2011-07◆ Germany: EUR 500m for Global Tech I offs…
“7 July 2011 [...] A consortium of commercial banks and the European Investment Bank (EIB) signed the finance contract for the Global Tech I project in Hamburg today. The external borrowing requirement…”
supportsFinal investment decisionTurbinesTotal capacity
Trade press6
[3]
Offshore Wind Biz2012-09◆ Germany: First Tripod Foundations Head t…
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionSite rightsFoundationassembly and staging
[4]
Offshore Wind Biz2015-09-02◆ Global Tech I Officially Turned On | Off…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationTurbinesTotal capacity
[6]
Offshore Wind Biz2022-12-15◆ GE Ventures Acquires Stake in Global Tec…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacity
[8]
Power Technology (GlobalData)2024-10-14◆ Power plant profile: Global Tech 1, Germ…
Press report — cited, not quoted; read it at the source link.
supportsco-owner
[10]
unknown
supportsCoordinates
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[9]
Wikipedia2024
“HVDC BorWin2 is a high voltage direct current (HVDC) link [...] DC voltage plus-minus 300 kV [...] Each of the two 300 kV cables linking BorWin Beta to the onshore substation has a total length of 200…”
supportsStatusConnection point