Hohe See

Located 90km north of Borkum. Was Germany's largest single OWF at COD.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2007’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Permit holder: EOS Offshore AG — held by wpd offshore GmbH per the record's source 'wpd-eos-oow-sale-to-enbw-2008'. BSH Plangenehmigung EnBW Hohe See, 30 Nov 2016, reciting the history: 'Die ursprüngliche TdV, die EOS Offshore AG, zum Zeitpunkt der Antragstellung bis zum 11.06.2003 die Firma innoVent GmbH, reichte am 02.07.2001 … einen Antrag … ein. Mit Bescheid vom 05.07.2006 …' — the original permit (as 'Hochsee Windpark Nordsee') was granted to EOS Offshore AG; EnBW's acquisition is not yet a recorded deal. Owner: the 2008 sale names EOS Offshore AG a wpd offshore GmbH subsidiary; whether wpd held it at the 2006 grant is not stated — the owner is as of the FIRST held document (13 May 2008).Party of record at origination Jul 2006 · auction recordView the source for Consent grantedConsent granted 30 Nov 2016 ◆View the source for Final investment decisionFinal investment decision Feb 2017 ◆View the source for Offshore constructionOffshore construction Apr 2018 ◆View the source for Onshore constructionOnshore construction 2018 ◆View the source for First powerFirst power Jul 2019 ◆View the source for Commercial operationCommercial operation Oct 2019 ◆Permit holder: EOS Offshore AG — held by wpd offshore GmbH per the record's source 'wpd-eos-oow-sale-to-enbw-2008'. BSH Plangenehmigung EnBW Hohe See, 30 Nov 2016, reciting the history: 'Die ursprüngliche TdV, die EOS Offshore AG, zum Zeitpunkt der Antragstellung bis zum 11.06.2003 die Firma innoVent GmbH, reichte am 02.07.2001 … einen Antrag … ein. Mit Bescheid vom 05.07.2006 …' — the original permit (as 'Hochsee Windpark Nordsee') was granted to EOS Offshore AG; EnBW's acquisition is not yet a recorded deal. Owner: the 2008 sale names EOS Offshore AG a wpd offshore GmbH subsidiary; whether wpd held it at the 2006 grant is not stated — the owner is as of the FIRST held document (13 May 2008). 2006-07 ORIGINATIONwpd offshore GmbH → EnBW — 100% 2008-05-13 ACQUISITIONEnBW → Enbridge — 49.9% 2017-02 FARMDOWNEnbridge → CPP Investments — 24.5% · closed 2018-08 2018-05 CPP Investments → Enbridge — 24.5% · closed 2023-12 2023-11 TODAYwpd offshore GmbH wpd offshore GmbH wpd offshore GmbH exited 2008-05-13EnBW — 50.1% today · operator EnBW EnBW 50.1%Enbridge — 49.9% today · investor Enbridge Enbridge 49.9%CPP Investments CPP Investments CPP Investments exited 2023-11Permit holder: EOS Offshore AG — held by wpd offshore GmbH per the record's source 'wpd-eos-oow-sale-to-enbw-2008'. BSH Plangenehmigung EnBW Hohe See, 30 Nov 2016, reciting the history: 'Die ursprüngliche TdV, die EOS Offshore AG, zum Zeitpunkt der Antragstellung bis zum 11.06.2003 die Firma innoVent GmbH, reichte am 02.07.2001 … einen Antrag … ein. Mit Bescheid vom 05.07.2006 …' — the original permit (as 'Hochsee Windpark Nordsee') was granted to EOS Offshore AG; EnBW's acquisition is not yet a recorded deal. Owner: the 2008 sale names EOS Offshore AG a wpd offshore GmbH subsidiary; whether wpd held it at the 2006 grant is not stated — the owner is as of the FIRST held document (13 May 2008). wpd offshore GmbH → EnBW — 100% 100%EnBW → Enbridge — 49.9% 49.9%Enbridge → CPP Investments — 24.5% · closed 2018-08 24.5%CPP Investments → Enbridge — 24.5% · closed 2023-12 24.5%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2019→2019-10 · 2 recorded revisions · held within the year (first announced 2019, latest 2019-10)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2019-10
Offshore construction2018-04 → 2019-10
Construction ports
PortCuxhaven ∅·quay 734 m · crane 650 t · draft 12.7 m
PortVlissingen ◆·marshalling · quay 1740 m · crane 1200 t
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationHohe See Offshore Substation·155/33 kV · in service 2018 · owner EnBW (wind farm owner; farm-owned platform, not TSO-owned)
HVDC systemBorWin3·900 MW · ±320 kV · in service 2019-08 · shared with Global Tech I
Converter supplierSiemens (HVDC PLUS); Petrofac EPCI·BorWin3 · Drydocks World, Dubai, UAE · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
201820192020202120222023202420252026developer’s stated start 2019-Q4nowBorWin3BorWin3first planned 2019first planned 2019in service 2019-08in service 2019-08Hohe See Offshore SubstationHohe See Offshore Substationin service 2018in service 2018

Sources & verification

Rests on 11 sources (10 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2016-11-30◆ Genehmigungsbescheid Offshore-Windpark E…
“Az: 5111/EnBW Hohe See/PFV/M5317 Hamburg, den 30.11.2016 [...] Gegenstand dieser Plangenehmigung sind 71 (einundsiebzig) Windenergieanlagen ( im Folgenden: WEA) mit folgenden Parametern: Rotordurchmes…”
supportsConsentTurbinesUnit capacityFoundationCoordinates+1 more
[14]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Windpark Hohe See": 71 units, 521.85 MW gross, statuses {'In Betrieb': 71}, operators ['EnBW Hohe See GmbH & Co. KG'], commissioned 2019-07-15..2019-10-01, planned None..None.”
supportsRegister entry
Operator4
[3]
EnBW Energie Baden-Württemberg AG2019-08◆ Construction of “EnBW Hohe See” offshore…
“EnBW has installed all 71 wind turbines of its offshore wind farm 'Hohe See' in the German North Sea. 27 turbines have already been put into operation and feed electricity into the grid. Both wind far…”
supportsTurbines
[5]
EnBW Energie Baden-Württemberg AG2020-01◆ Germany’s biggest wind farm connected to…
“The Hohe See offshore wind farm has already been in operation since October 2019. Now its smaller neighbour Albatros is also producing electricity.”
supportsCommercial operationCOD history
[12]
EnBW2026-06◆ EnBW — enbw factbook 2026
“Baltic 1 Baltic 2 Hohe See Albatros He Dreiht Dreekant Type of turbine 21 x Siemens 2.3 MW 80 x Siemens 3.6 MW 71 x Siemens 7.35 MW 16 x Siemens 7.35 MW 64 x Vestas 15 MW n/a Total capacity in MW 48.3…”
supportsoperatorinvestorTotal capacity
[18]
Unternehmensregister2026-07-10◆ EnBW Hohe See GmbH & Co. KG, Biberach an…
“Die EnBW Hohe See GmbH & Co. KG mit Sitz in Biberach a. d. Riß, eingetragen im Handelsregister des Amtsgerichts Ulm (HRA 727396), ist eine große Personenhandelsgesellschaft.”
supportsMechanismDetail
Trade press5
[2]
offshoreWIND.biz2017-02-17
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[4]
offshoreWIND.biz2019-07-16
Press report — cited, not quoted; read it at the source link.
supportsFirst powerTotal capacity
[6]
offshoreWIND.biz2018-04-11
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionSite rightsmarshalling
[8]
Power Technology / GlobalData2020
Press report — cited, not quoted; read it at the source link.
supportsModelStatusConnection pointWater depthDistance from shore
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed