Trianel Windpark Borkum I

Located 45km north of Borkum. Phase 2 (Trianel Windpark Borkum II, 200 MW) commissioned 2020.

Project timeline verified milestones only — each date carries its provenance mark

Dashed tick marks today (13 Oct 2026).
Announced-COD history: 2015-02-01→2015-Q3→2015-09 · 3 recorded revisions · slipped +0.6 yr (first announced 2015-02-01)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2015-09
Offshore construction2011-09 → 2015-09
Construction ports
PortEemshaven ◆·pre-assembly and load-out · quay 5000 m · crane 50 t · draft 14 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationUmspannplattform Trianel Windpark Borkum·33/155 kV · in service 2013 · owner Infrastruktur Windkraftwerk Borkum GmbH & Co. KG (IWB) — farm-side operator, not TSO-owned · also serves Trianel Windpark Borkum II
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20132014201520162017201820192020202120222023202420252026developer’s stated start 2015-09nowUmspannplattform Trianel Windpark BorkumUmspannplattform Trianel Windpark…in service 2013in service 2013

Sources & verification

Rests on 12 sources (16 primary) · ◆ 7 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[7]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2008-06-13◆ Genehmigungsbescheid Offshore-Windpark T…
“werden Errichtung und Betrieb von 80 Windenergieanlagen (WEA) einschließlich Nebenanlagen im Bereich der deutschen ausschließlichen Wirtschaftszone (AWZ) in der Nordsee nach Maßgabe der folgenden Nebe…”
supportsConsentCoordinatesConsent granted
[12]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Trianel Windpark Borkum": 40 units, 200.0 MW gross, statuses {'In Betrieb': 40}, operators ['Trianel Windkraftwerk Borkum GmbH & Co. KG'], commissioned 2015-02-01..2015-07-16, planned None..…”
supportsRegister entry
Operator7
[1]
Trianel Windkraftwerk Borkum GmbH & Co. KG2026-06-10
"40 wind turbines, each with 5 MW, stand firmly on so-called tripods on the seabed." "45 km off the island of Borkum" "water depth: 25-35 m" "Autumn 2015: Beginning of continuous operation."
supportsTurbinesUnit capacityTotal capacityFoundationWater depth+1 more
[2]
Trianel Windkraftwerk Borkum GmbH & Co. KG2026-06-10
"December 2010: project financing agreements are signed." "September 2011: Start of construction work. First pile driving at sea." "February 2015: the first plants are connected to the grid and put in…
supportsOffshore constructionFirst powerSite rightsModelpre-assembly and load-out
[4]
Trianel GmbH (via Presseportal)2015-09-01◆ Inbetriebnahme des Trianel Windpark Bork…
“01.09.2015 – 09:45 [...] Johannes Remmel, Minister für Klimaschutz, Umwelt, Landwirtschaft, Natur- und Verbraucherschutz des Landes Nordrhein-Westfalen, hat am 1. September gemeinsam mit Trianel und d…”
supportsCommercial operationCOD history
[5]
Trianel GmbH (via Presseportal)2010-12-21◆ Baubeschluss und Finanzierungsvereinbaru…
“21.12.2010 – 13:38 [...] Die 34 Gesellschafter aus Deutschland, Österreich, den Niederlanden und der Schweiz haben auf der TWB Gesellschafterversammlung den Baubeschluss für den ersten Bauabschnitt de…”
supportsFinal investment decision
[13]
Bundesanzeiger2017-10-26◆ Trianel Windkraftwerk Borkum GmbH & Co. …
“Die Trianel Windkraftwerk Borkum GmbH & Co. KG (TWB) wurde am 9. April 2008 gegründet.”
supportsMechanismDetail
[17]
Unternehmensregister2023-10-26◆ Trianel Windkraftwerk Borkum GmbH & Co. …
“Die Trianel Windkraftwerk Borkum GmbH & Co. KG (TWB) wurde am 9. April 2008 gegründet.”
supportsMechanismDetail
[18]
Unternehmensregister2025-11-11◆ Trianel Windkraftwerk Borkum GmbH & Co. …
“Die Trianel Windkraftwerk Borkum GmbH & Co. KG (TWB) wurde am 9. April 2008 gegründet.”
supportsMechanismDetail
Trade press2
[8]
Offshore Wind (trade press)2015-07-28
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection point
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[10]
Wikipedia2024
supportsoperator