Merkur Offshore

Located 45km north of Borkum. First commercial GE Haliade-150 6MW deployment in Germany.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted Aug 2009 ◆Permit holder: Nordsee Offshore MEG I GmbH — held by Windreich AG per the record's source 'infrared-merkur-case-study'. BSH Genehmigung MEG Offshore I, Aug 2009 — 'Auf den Antrag der Nordsee Offshore MEG I GmbH … werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' The project became Merkur Offshore under later owners; that transfer is not yet a recorded deal. Owner: InfraRed names Windreich 'the original developer'; Nordsee Offshore MEG I GmbH was its project company. The consortium bought the project out of the Windreich insolvency in 2016 (record of deals).Party of record at origination Aug 2009 · auction recordView the sources for Final investment decisionFinal investment decision Aug 2016 ◆View the source for Offshore constructionOffshore construction Apr 2017 ◆View the source for First powerFirst power Jun 2018 ◆View the source for Commercial operationCommercial operation Jun 2019 ◆Permit holder: Nordsee Offshore MEG I GmbH — held by Windreich AG per the record's source 'infrared-merkur-case-study'. BSH Genehmigung MEG Offshore I, Aug 2009 — 'Auf den Antrag der Nordsee Offshore MEG I GmbH … werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' The project became Merkur Offshore under later owners; that transfer is not yet a recorded deal. Owner: InfraRed names Windreich 'the original developer'; Nordsee Offshore MEG I GmbH was its project company. The consortium bought the project out of the Windreich insolvency in 2016 (record of deals). 2009-08 ORIGINATIONWindreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 2016-08 ACQUISITIONPartners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 2019-12 InfraRed Capital Partners (co-investors) → TRIG — 11.0% 2022-12 TODAYWindreich AG (in insolvency) Windreich AG Windreich AG exited 2016-08Partners Group Partners Group Partners Group exited 2019-12InfraRed Capital Partners (co-investors) InfraRed Capital Partne… InfraRed Capital Partne… exited 2022-12DEME Concessions DEME Concessions DEME Concessions exited 2019-12GE Energy Financial Services GE Energy Financial Ser… GE Energy Financial Ser… exited 2019-12ADEME ADEME ADEME exited 2019-12APG — 64.3% today APG APG 64.3%TRIG — 35.7% today TRIG TRIG 35.7%Permit holder: Nordsee Offshore MEG I GmbH — held by Windreich AG per the record's source 'infrared-merkur-case-study'. BSH Genehmigung MEG Offshore I, Aug 2009 — 'Auf den Antrag der Nordsee Offshore MEG I GmbH … werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' The project became Merkur Offshore under later owners; that transfer is not yet a recorded deal. Owner: InfraRed names Windreich 'the original developer'; Nordsee Offshore MEG I GmbH was its project company. The consortium bought the project out of the Windreich insolvency in 2016 (record of deals). Windreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 Windreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 Windreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 Windreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 Windreich AG (in insolvency) → Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME — 100.0% · closed 2016-11 100% → consortiumPartners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 Partners Group / InfraRed Capital Partners / DEME Concessions / GE Energy Financial Services / ADEME → APG / TRIG — 100.0% · closed 2020-05 100% → consortiumInfraRed Capital Partners (co-investors) → TRIG — 11.0% 11%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2019-03→2019→2019-06 · 3 recorded revisions · held within the year (first announced 2019-03, latest 2019-06)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2019-06
Offshore construction2017-04 → 2019-06
Construction ports
PortEemshaven ◆·marshalling · quay 5000 m · crane 50 t · draft 14 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationMerkur Offshore Substation·in service 2018 · owner Merkur Offshore wind farm owner (farm-owned platform)
HVDC systemDolWin3·900 MW · ±320 kV · in service 2018-Q3 · shared with Borkum Riffgrund 2
Converter supplierGE Vernova (contracted as Alstom Grid; became GE Grid Solutions / GE Grid GmbH)·DolWin3 · Nordic Yards, Warnemünde (Germany) — first steel cut 9 October 2014 · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2017201820192020202120222023202420252026developer’s stated start 2019-06nowDolWin3DolWin3first planned 2017first planned 2017in service 2018-Q3in service 2018-Q3Merkur Offshore SubstationMerkur Offshore Substationin service 2018in service 2018

Sources & verification

Rests on 13 sources (12 primary) · ◆ 8 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2009-08◆ Genehmigung Offshore-Windpark Merkur Off…
“Auf den Antrag der Nordsee Offshore MEG I GmbH ... werden Errichtung und Betrieb von 80 Windenergieanlagen (WEA) einschließlich Nebenanlagen im Bereich der deutschen ausschließlichen Wirtschaftszone (…”
supportsConsentCoordinatesConsent granted
[16]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Merkur Offshore": 66 units, 405.9 MW gross, statuses {'In Betrieb': 66}, operators ['Merkur Offshore GmbH'], commissioned 2018-07-23..2019-05-16, planned None..None.”
supportsRegister entry
Operator4
[2]
DEME Group2016◆ Merkur project confirms financial close
“On behalf of its shareholders, Merkur Offshore GmbH is pleased to announce that the 396-megawatt Merkur offshore wind development project has confirmed financial close. [...] Offshore foundations inst…”
supportsFinal investment decision
[4]
DEME Group2019-12-10
“396-MW offshore wind farm located c. 45 kilometres north of Borkum Island in the German North Sea. The project comprising of 66 General Electric ("GE") Haliade-150 6-MW offshore wind turbines was full…”
supportsDistance from shore
[8]
DEME Group2024-01
“water depths ranging from 27 m to 33 m [...] loaded the monopiles and transition pieces in the port of Eemshaven in the Netherlands and transported them offshore.”
supportsFoundationWater depthmarshalling
[20]
Unternehmensregister2024-12-30◆ Merkur Offshore GmbH, Zossen - Jahresabs…
“Firmenname laut Registergericht: Merkur Offshore GmbH ... Firmensitz laut Registergericht: Zossen ... Registergericht: Potsdam ... Register-Nr.: HRB 34552”
supportsMechanismDetail
Trade press7
[3]
offshoreWIND.biz2019-12-10◆ Merkur Offshore Wind Farm to Change Hand…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historyTurbinesModelUnit capacity+1 more
[7]
Energy Central2022-12-21◆ Renewable Energy M&A: TRIG acquires an a…
“Following deal completion, Dutch pension managers APG and TRIG will own a 64.3% and 35.7% stake in the project, respectively. The Renewables Infrastructure Group (TRIG) acquired the stake from UK-base…”
supportsowner
[9]
offshoreWIND.biz2017-04-20
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionSite rights
[10]
offshoreWIND.biz2020-10-13
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection point
[11]
Offshore Wind Biz2016-08-12◆ Amscap Advises Merkur to Financial Close
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[13]
offshoreWIND.biz2018-06-04◆ Merkur Produces First Electricity | Offs…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed