Jammerland Bugt

Open-door project located south of Kalundborg, between Asnaes and Reerso peninsulas in the Great Belt area. 16 turbines at 256m height.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

—
on hold — no credible date; the chart shows when a restarted project might complete
Chance of delivery
≈15% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. Technical complexity and no offtake contract yet pull this one slightly below that. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈15%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2024’25’26View the source for Consent appliedConsent applied 15 Mar 2024 ◆View the source for Consent grantedConsent granted 17 Dec 2024 ◆View the source for On holdOn hold Aug 2026 ◇No origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDEuropean Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 2024-01 FARMDOWNTotalEnergies → None — 85% 2026-08 WITHDRAWALTODAYEuropean Energy — 15% today European Energy European Energy 15%SONFOR SONFOR SONFOR exited 2024-01TotalEnergies — 85% today TotalEnergies TotalEnergies 85%European Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 European Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 85% → consortium
Dashed tick marks today (13 Oct 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open

Open-door nearshore; electricity to be sold on the wholesale electricity market or through Corporate PPAs (CPPAs) per developer. No signed offtake contract as of 2026-06-15. Not a CfD route. ◇

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Nordsøen Syd (North Sea South) ◇
expected H2 2028 · planned · the round’s published documents do not name this project
announced

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation not started
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

Rests on 12 sources (5 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[3]
Energistyrelsen (Danish Energy Agency)2024-12-17◆ Energistyrelsen giver tilladelse til at …
“Energistyrelsen udsteder etableringstilladelse til Jammerland Bugt Kystnær Havmøllepark ... projektet vil have en samlet kapacitet på 240 MW ... Tilslutningspunktet bliver Energinets eksisterende højs…”
supportsConsentSite rightsTotal capacityConsent appliedConsent granted
Operator3
[4]
TotalEnergies2024-01-23◆ Renewables: TotalEnergies and European E…
“acquisition by TotalEnergies of a 85% equity stake in the Jammerland Bugt offshore wind project (240 MW) ... have obtained exclusivity and grid connection permits ... The electricity generated by thes…”
supportsDetailStatusConnection pointOfftake history
[7]
European Energy2024-12◆ TotalEnergies, European Energy and SONFO…
supportsowner
[8]
European Energy2025-03
supportsTurbinesUnit capacityTotal capacity
Auction pipeline1
[17]
Danish Energy Agency (Energistyrelsen)2025-11◆ dea-3-tenders-2025
DEA — Nordsøen Syd, >=1,000 MW, bid deadline autumn 2028.
supportsNordsøen Syd (North Sea South)
Trade press6
[9]
offshoreWIND.biz2024-12
Press report — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[10]
4C Offshore2025
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[11]
Global Energy Monitor2026-07-02
supportsCoordinates
[12]
GEBCO Compilation Group2020
supportsWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[16]
EnergyWatch2026-08-06◆ TotalEnergies abandoning Danish offshore…
Copyrighted source — cited, not quoted; read it at the source link.
supportsOn hold
Unverified import1
[1]
unknown
supportsTurbinesUnit capacityTotal capacityFoundationWater depth+1 more