OranjeWind (Hollandse Kust West Site VII)
TotalEnergies will use its share of power for 350 MW electrolyser producing ~40,000 tonnes/year green hydrogen for European refineries.
Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
RWE — 50% ◆
TotalEnergies — 50% ◆Location
North Sea
Technology
Capacity
795 MW ◆
Turbines
53 × 15 MW ◆
Model
Vestas V236 15-0 ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
Hollandse Kust (west) Sites VI & VII · 2022 ·
Water depth
22–32 m ≈
Distance from shore
53 km ◆
Wind speed
9.9 m/s @ 150 m ≈
Revenue & grid
Offtake
Merchant ◆
Grid
Secured · Sep 2023 ◆
Connection
TenneT Hollandse Kust (west) Beta offshore substation (700 MW … ◆
Schedule
FID
Jul 2024 ◆
COD · announced
2028 ◆
COD · Hafrok
2028 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2028
expected year of commercial operation
Chance of delivery
≈97%
estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
| Year | Probability |
|---|---|
| 2027 | 1.3% |
| 2028 (expected) | 75.4% |
| 2029 | 21.7% |
| 2030 | 1.6% |
| Stated | Announced COD |
|---|---|
| 2026-09-01 | 2028 (held since 2024-07-24, 4 statements) |
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in
2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2027 Q3; the faster quarter of similar projects would be done by 2026 Q4, the slower quarter not until 2028 Q3.3
Result
Expected commercial operation
2028, likely range 2027–2029 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈97%, which rates it
Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2022-12
Hollandse Kust (west) Sites VI & VII
- Awarded to
- Oranje Wind Power II B.V. (RWE; later TotalEnergies co-owner)
- Basis
- integrated tender
From the auction results — the round that created the project.
Farmdown · 2024-07
RWE → TotalEnergies 50%
- Stake
- 50%
- Consideration
- not disclosed
- Announced
- 2024-07
- Project stage
- FID
TotalEnergies acquired 50% of OranjeWind from RWE, announced 24 July 2024. Partnership agreement signed and FID taken simultaneously. TotalEnergies intends to use its share of renewable power to supply ~350 MW of electrolysers producing ~40,000 t/yr of green hydrogen for its Northern European refineries. Construction scheduled to start 2026; full commissioning expected early 2028. Deal value not disclosed. By December 2025, the JV was jointly signing construction contracts (ARC Marine reef cubes).
Evidence
- totalenergies.com — Netherlands: TotalEnergies acquires a stake in the OranjeWin ↗ 2024-07 ◆ held
- RWE — RWE — rwe interim report h1 2024 ↗ 2024-Q2 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (13 Oct 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2028, unchanged) · the full guidance history is in the delivery chart above
Revenue & offtake the regime the project was built under
Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from sourced statements and Hafrok’s registers
Installation under way
Installation · on record
StageUnder Construction
Offshore constructionstarted 2026-03
Turbinesinstallation not started◆as of 2026-09-01 (date published) · reported by RWEExpected start of operation2028
Construction ports
PortBuss Terminal Eemshaven ◆·turbines · quay 5000 m · crane 50 t · draft 14 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationHollandse Kust (west Beta)·planning · owner TenneT
Sources & verification
Rests on 14 sources (12 primary) · ◆ 12 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[2]
RVO (Netherlands Enterprise Agency)2021-06◆ Hollandse Kust (west) Wind Farm Zone - P…
“Hollandse Kust (west) Wind Farm Zone (HKWWFZ) is located approximately 28.6 nautical miles (53 km) off the west coast of the Netherlands.”
supportsDistance from shoreCoordinates
[3]
RVO (Netherlands Enterprise Agency)2022-12◆ RVO Hollandse Kust West VI & VII results
“On 10 November 2022, Minister for Climate and Energy Rob Jetten announced that the permit for Wind Farm Site VII of the Hollandse Kust (west) Wind Farm Zone has been awarded to Oranje Wind Power II, a…”
supportsConsentMechanismDetailConsent granted
Operator8
[1]
Netherlands Ministry of Economic Affairs and Climate Policy2021-11-26◆ Kavelbesluit VII windenergiegebied Holla…
“Kavel VII in windenergiegebied Hollandse Kust (west) wordt aangewezen als locatie voor een windpark met een totaal geïnstalleerd vermogen van minimaal 693 MW.”
supportsConsentFoundationConsent appliedConsent granted
[4]
RWE AG2022-11-10◆ Hollandse Kust West VII: RWE successful …
“RWE wins Dutch support-free offshore wind tender: The company has received the permit to build a large-scale offshore wind farm – Hollandse Kust West (HKW) VII. The site is located in the North Sea, a…”
supportsBackground
[5]
RWE AG2024-07-24◆ TotalEnergies and RWE join forces to imp…
“RWE and TotalEnergies have also taken the investment decision to build the OranjeWind offshore wind farm, which will have an installed capacity of 795 megawatts (MW). [...] Each partner has 50% stake …”
supportsFinal investment decisionTurbinesModelUnit capacityTotal capacity+4 more
[7]
RWE AG2023-09-12◆ RWE and TenneT sign agreements for conne…
“Network operator TenneT and energy company RWE have signed agreements for an offshore grid connection of OranjeWind, a wind farm to be built 53 kilometres off the Dutch coast. The Connection & Transmi…”
supportsStatusConnection point
[8]
RWE AG2024-12-10◆ RWE and TotalEnergies choose Eemshaven a…
“RWE and TotalEnergies have selected the port of Eemshaven in the northern Dutch province of Groningen as the base for turbine assembly and construction work for their joint offshore wind project Oranj…”
supportsturbines
[11]
[14]
RWE2026-09-01◆ First monopile successfully installed at…
“The OranjeWind project has successfully installed the first monopile in the Dutch North Sea. ... Installation of all 53 monopiles is expected to be completed by early 2027. ... The monopile was loaded…”
supportsCOD history
[15]
Sif2026-09-01◆ First load-out for OranjeWind
“the first monopile has been loaded out from Sif’s Maasvlakte terminal. Sif is supplying 53 TP-less (transition piece-less) monopiles for OranjeWind, a joint venture between RWE and TotalEnergies.”
supportsBackground
OEM1
[6]
Vestas2024-07-29◆ Vestas secures 795 MW order for the Oran…
“Vestas has received a firm wind turbine order for the OranjeWind offshore wind farm, formerly known as Hollandse Kust West VII, in the Netherlands. Vestas will be supplying 53 V236-15.0 MW wind turbin…”
supportsTurbinesModelUnit capacityTotal capacity
Trade press3
[10]
offshoreWIND.biz2026-03-30◆ Seabed Preparation Starts Ahead of Const…
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionCommercial operation