Docking Shoal
Located in the outer Wash area approximately 14 km off the North Norfolk/Lincolnshire coastline. Crown Estate Round 2 lease awarded to Centrica in 2004.
Status
Cancelledlifecycle stage
Ownership
CECentrica — 100% ◇
Location
North Sea
Technology
Capacity
540 MW ◇
Turbines
108 × 5 MW ◇
Foundation
Monopile ◇
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 2 · 2003 ·
Water depth
20–30 m ◇
Distance from shore
14 km ◇
Wind speed
9.5 m/s @ 100 m ≈
Revenue & grid
Offtake
Other project cancelled ◆
Grid
No agreement ◆
Schedule
COD
—
Cancelled
6 Jul 2012 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2003-12
Crown Estate Round 2
- Awarded to
- Centrica
- Basis
- seabed award
From the auction results — the round that created the project.
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Installation how the build is going · from sourced statements and Hafrok’s registers
Installation not started
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
Rests on 6 sources (2 primary) · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
UK Government (DECC)2012-07-06◆ New offshore wind farms will bring huge …
"We have also shown that we are mindful of other consequences, such as the impact on bird populations, in deciding that it would not be appropriate to consent all three applications." The application …
supportsConsentCancelledMechanismDetailStatus
[6]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2516: Site Name "Docking Shoal A", Development Status "Application Refused", Installed Capacity 540 MWelec, Operator "Centrica"”
supportsRegister entry
Trade press3
[2]
4C Offshore
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacityFoundationWater depth+2 more
[3]
Windpower Monthly2012-07
Press report — cited, not quoted; read it at the source link.
supportsBackgroundStatus note
[5]
Encyclopaedic1
[4]