Lincs

Located 8km off Skegness, Lincolnshire. Round 2 development.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2004’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 2 — awarded to CentricaCrown Estate Round 2 Dec 2003 · auction recordView the source for Consent grantedConsent granted Oct 2008 ◆View the source for Final investment decisionFinal investment decision Oct 2009 ◆View the source for Onshore constructionOnshore construction 2010 ◆View the source for Offshore constructionOffshore construction Mar 2011 ◆View the source for First powerFirst power Aug 2012 ◆View the source for Commercial operationCommercial operation 1 Aug 2013 ◆Crown Estate Round 2 — awarded to Centrica 2003-12 ORIGINATIONCentrica → Ørsted / Siemens Project Ventures — 50% · €417m · closed 2010-01 2009-12 FARMDOWNCentrica / Siemens Project Ventures → Green Investment Group (GIB Offshore Wind Fund) — 75% · €849m · closed 2017-Q1 2017-01 ACQUISITIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDMacquarie European Infrastructure Fund 5 (MEIF5) → Octopus Energy Generation (Octopus Renewables Infrastructure Trust / Sky fund) — 15.5% 2022-09-16 TODAYCentrica Centrica Centrica not among today’s recorded owners — no sale recordedØrsted — 25% today · operator Ørsted Ørsted 25%Siemens Project Ventures Siemens Project Ventures Siemens Project Ventures exited 2017-01Green Investment Group — 44% today Green Investment Group Green Investment Group 44%Macquarie European Infrastructure Fund 5 (MEIF5) Macquarie European Infr… Macquarie European Infr… exited 2022-09-16Octopus Energy Generation — 31% today Octopus Energy Generati… Octopus Energy Generati… 31%Crown Estate Round 2 — awarded to Centrica Centrica → Ørsted / Siemens Project Ventures — 50% · €417m · closed 2010-01 Centrica → Ørsted / Siemens Project Ventures — 50% · €417m · closed 2010-01 50% → consortiumCentrica / Siemens Project Ventures → Green Investment Group (GIB Offshore Wind Fund) — 75% · €849m · closed 2017-Q1 Centrica / Siemens Project Ventures → Green Investment Group (GIB Offshore Wind Fund) — 75% · €849m · closed 2017-Q1 75% → consortiumTransfer(s) not in Hafrok's record — shown as a gap, never guessed. Macquarie European Infrastructure Fund 5 (MEIF5) → Octopus Energy Generation (Octopus Renewables Infrastructure Trust / Sky fund) — 15.5% 15.5%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2013-Q3→2013-08-01 · 2 recorded revisions · held within the year (first announced 2013-Q3, latest 2013-08-01)

Revenue & offtake the regime the project was built under

Offtake regime on record
RegimeRenewables Obligation: 2.0 ROCs/MWh (offshore wind, accredited 2013, ROO 2009 banding — rate per policy table, project-specific Ofgem accreditation not confirmed)
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2013-08-01
Offshore construction2011-03 → 2013-08-01
Construction ports
PortPort of Hull (ABP) ◆construction base
PortPort of Grimsby ◆operations base
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationLincs Offshore Substation Platform (OSP)·132/33 kV · in service 2012 · owner TC Lincs OFTO Ltd (Transmission Capital Partners / Transmission Investment); assets built by Lincs Wind Farm Limited (Centrica / Ørsted / Siemens Project Ventures JV)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
201220132014201520162017201820192020202120222023202420252026developer’s stated start 2013-Q3nowLincs Offshore Substation Platform (OSP)Lincs Offshore Substation Platfor…in service 2012in service 2012

Sources & verification

Rests on 14 sources (12 primary) · ◆ 8 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[11]
Ofgem2014-11-04◆ Ofgem grants £308 million transmission a…
“Ofgem grants £308 million transmission assets licence for Lincs wind farm on 4 November 2014. TC Lincs OFTO Limited granted transmission licence. The wind farm comprises 75 3.6MW turbines, giving a ca…”
supportsTurbinesUnit capacityTotal capacityStatusConnection point+1 more
[17]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2513: Site Name "Centrica (Lincs)", Development Status "Operational", Installed Capacity 270 MWelec, Operator "Ørsted"”
supportsRegister entry
Operator4
[1]
Ørsted A/S (then DONG Energy)2017-01-12◆ DONG Energy to provide operation and mai…
“DONG Energy has today agreed to enter into a long-term contract to provide operation and maintenance ('O&M') services to Lincs Offshore Wind Farm ('Lincs'), a 270MW offshore wind farm located off the …”
supportsOnshore constructionOffshore constructionCommercial operationCOD historyTurbines+3 more
[18]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000215: "Lincs Offshore Wind Farm", Status "Built", MW Connected 265, Effective From n/a, Customer "LINCS WIND FARM LIMITED"”
supportsRegister entry
[19]
Macquarie Asset Management2022-09-16◆ Macquarie Asset Management sells minorit…
“Macquarie European Infrastructure Fund 5's minority stake in Lincs, which it has held since 2017, has been acquired by Octopus Renewables Infrastructure Trust and Sky (ORI SCSp), funds managed by Octo…”
supportsowner
[20]
Octopus Energy2023-02◆ Octopus Energy makes more waves in offsh…
“Octopus further invests in the 270 MW Lincs offshore wind farm off the east coast of England, increasing Octopus' stake in Lincs to 31%. Octopus Energy Generation's fund management team previously man…”
supportsowner
OEM1
[10]
Siemens AG (UK)2010
“Siemens Energy won a major order to implement grid connection for the Lincs offshore wind farm. The offshore substation steps up voltage from 33kV (turbines) to 132kV transmission voltage. High-voltag…”
supportsStatusConnection point
Trade press7
[6]
Offshore Wind Biz2013-08-01◆ UK: Lincs Offshore Wind Farm Inaugurated…
Press report — cited, not quoted; read it at the source link.
supportsFirst powerDistance from shoreoperations base
[7]
Offshore Wind Biz2013-04-02
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacity
[8]
Proactive Investors2009-10-28◆ Centrica to start construction of 270 me…
"Centrica plc announced that its 270 megawatt Lincs offshore wind project has received final investment approval, and that construction is expected to begin in 2010." ... Centrica plc (LSE: CNA) annou…
supportsFinal investment decision
[12]
NS Energy Business (GlobalData)2024
Press report — cited, not quoted; read it at the source link.
supportsConsentModelFoundationWater depthDistance from shore+3 more
[14]
Transmission Capital Partners / Transmission Investment2024
“TC Lincs OFTO Ltd acquired transmission assets and received its transmission licence on November 11, 2014. Transfer value approximately £307.7 million. Export cables operate at 132kV with combined off…”
supportsStatusConnection point
[15]
Macquarie Group2022-09
“Macquarie Green Investment Group Renewable Energy Fund 1 will continue to manage a 44 per cent stake in Lincs”
supportsoperator
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed