Nobelwind

Bligh Bank II, 47 km from Zeebrugge. Parkwind's first JV with Sumitomo (39%). Meewind (19.9%).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2005’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to ParkwindBelgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) 2004 · auction recordView the sources for Consent grantedConsent granted 7 Oct 2015 ◆View the source for Final investment decisionFinal investment decision Oct 2015 ◆View the source for Offshore constructionOffshore construction Apr 2016 ◆View the source for First powerFirst power Jan 2017 ◆View the source for Commercial operationCommercial operation May 2017 ◆Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to Parkwind 2004 ORIGINATIONParkwind, Sumitomo Corporation, Meewind — stake not disclosed · closed 2015-10 2014-06 JV FORMATIONParkwind (Virya Energy / Colruyt Group) → Parkwind (JERA) — 41.08% · closed 2023-07 2023-03 CORPORATEJERA, BP — stake not disclosed · closed 2025-08 2024-12 CORPORATESumitomo Corporation → JERA Nex bp — 39.02% 2026-07 TODAYParkwind — 80.1% today Parkwind Parkwind 80.1%Sumitomo Corporation Sumitomo Corporation Sumitomo Corporation exited 2026-07Meewind — 19.9% today Meewind Meewind 19.9%JERA Nex bp JERA JERA exited 2026-07BP BP BP exited 2024-12Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to Parkwind Parkwind, Sumitomo Corporation, Meewind — stake not disclosed · closed 2015-10 Parkwind (Virya Energy / Colruyt Group) → Parkwind (JERA) — 41.08% · closed 2023-07 JERA, BP — stake not disclosed · closed 2025-08 Sumitomo Corporation → JERA Nex bp — 39.02% 39.02%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2017-Q4→2017-05 · 2 recorded revisions · pulled forward -0.5 yr (first announced 2017-Q4)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2017-05
Offshore construction2016-04 → 2017-05
Construction ports
PortPort of Ostend ◆installation

Sources & verification

Rests on 11 sources (9 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator6
[1]
Sumitomo Corporation2015-10◆ Sumitomo, Parkwind, and Meewind Secure F…
“Sumitomo Corporation: 39.02% ... 165 MW total production capacity ... 50 wind turbines rated at 3.3 MW each ... North Sea, approximately 45 km north of Belgian coast ... water depth: approximately 30 …”
supportsTurbinesUnit capacityTotal capacityDistance from shore
[2]
Korys (Nobelwind NV shareholder)2015-10
“Parkwind: 41.08% ... Sumitomo Corporation: 39.02% ... Meewind: 19.9% ... The financial close allows the project to go into its construction phase, due to start in spring 2016. ... concluded an electri…”
supportsFinal investment decision
[6]
FPS Economy (Belgian Federal Public Service)2024-01-01
“Operational since May 2017 ... Contains 50 turbines, each rated at 3.3 MW ... Total capacity: 165 MW ... Water depth: up to 37 meters ... Distance from coast: 46-52 km ... Foundation type: Monopile”
supportsCommercial operationCOD history
[10]
Nobelwind NV annual work report, hosted by MUMM (Royal Belgian Institute of Natural Sciences, OD Nature)2023-06-12
“The Bligh Bank offshore wind park zone is the initially Belwind concession zone, which has been split up into two separate concessions namely the Belwind and Nobelwind concession. In line with the Roy…”
supportsConsentConsent granted
[12]
Sumitomo Corporation2026-07-03◆ Sumitomo Corporation exits Belgian offsh…
“Sumitomo Corporation ... has decided to sell its equity stakes in three offshore wind power projects off the coast of Belgium: Northwind (joined in 2013), Nobelwind (joined in 2014), and Northwester 2…”
supportsowner
[15]
Royal Belgian Institute of Natural Sciences (MUMM)2026-10-12◆ MUMM permit register: milestones for the…
"NOBELWIND (BELWIND phase 2)" ... "Environmental permit" ... "Partial transfer from Belwind" ... "Minister responsible for the marine environment" ... "2015-10-07T02:00:00+02:00"
supportsConsentConsent granted
Trade press5
[3]
Power Technology (GlobalData)2017-06
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionTurbinesModelUnit capacityTotal capacity+7 more
[4]
offshoreWIND.biz2017-04-03◆ Jan De Nul Installs Last Nobelwind Turbi…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[7]
Norton Rose Fulbright2023-01-01
“The minimum price for Nobelwind (demerger of the initial Belwind domain concession) is EUR 107/MWh for power generated by the first 45 MW of installed capacity and EUR 90/MWh for generation resulting …”
supportsMechanismDetail
[9]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsowner
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed