Norther

Belgian EEZ, ~23 km from Zeebrugge, near Dutch EEZ border. Shareholders: Elicio (50%), Eneco (25%), Diamond Generating Europe/Mitsubishi (25%).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to Norther NVBelgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) Oct 2009 · auction recordView the sources for Consent grantedConsent granted 18 Jan 2012 ◆View the source for Final investment decisionFinal investment decision Dec 2016 ◆View the source for Offshore constructionOffshore construction Aug 2018 ◆View the source for First powerFirst power 2019-Q1 ◆View the source for Commercial operationCommercial operation May 2020 ◆Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to Norther NV 2009-10 ORIGINATION — stake not disclosed · closed 2016-12 2016-Q1 JV ENTRYTODAYNorther NV — 100% today · operator Norther NV Norther NV 100%Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank) — awarded to Norther NV
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2019→2019→2020-05 · 3 recorded revisions · slipped +0.9 yr (first announced 2019)

Revenue & offtake contract duration and price levels · money of the day

370 MW contracted — concession
● Concession · Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank)
Price€124/MWh ·Capacity370 MWAwardedOct 2009
Term20 yrs

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2020-05
Offshore construction2018-08 → 2020-05
Construction ports
PortPort of Ostend ∅installation base
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationNorther OHVS·33/220 kV · in service 2019 · owner Norther NV (the wind farm project company — NOT Elia)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20192020202120222023202420252026developer’s stated start 2020-Q2nowNorther OHVSNorther OHVSin service 2019in service 2019

Sources & verification

Rests on 10 sources (7 primary) · ◆ 7 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator5
[1]
Belgian Offshore Platform2016-12-19◆ Belgium's largest offshore wind turbine …
“50% Elicio, 25% Eneco and 25% Diamond Generating Europe comprise the partnership responsible for developing and operating the wind park. Financial close date: 19 December 2016. The installation compri…”
supportsoperatorFinal investment decisionTurbinesModelUnit capacity+2 more
[3]
Green Giraffe Advisory2020-05-27◆ Norther reaches technical completion and…
“On 27th May 2020 the Norther offshore wind farm officially transitioned to its operational phase as it reached technical completion. Norther is owned by three shareholders: Elicio NV holds 50%, with E…”
supportsCommercial operationCOD history
[14]
Royal Belgian Institute of Natural Sciences (MUMM)2026-10-12◆ MUMM permit register: milestones for the…
"NORTHER" ... "Environmental permit" ... "Granted" ... "Minister responsible for the marine environment" ... "2012-01-18T01:00:00+01:00"
supportsConsentConsent granted
[15]
Moniteur belge / Belgisch Staatsblad2017-02-22◆ Arrêté royal du 9 février 2017 modifiant…
“9 FEVRIER 2017. - Arrêté royal modifiant l'arrêté royal du 16 juillet 2002 ... b) 124,00 euros/MWh pour les installations faisant l'objet d'une concession domaniale attribuée à la SA Norther, pour la …”
supportsMechanismDetail
[16]
Norther NV2026-08-23◆ Norther NV - Shareholders
“Elicio NV is a 50% shareholder, via its fully owned vehicle Elnu NV. Elicio, a 100% subsidiary of Nethys, is a Belgian developer and operator of offshore and onshore wind farms. ... Eneco is a 50% sha…”
supports↳ parent
Financier1
[10]
European Investment Bank2016-05-18
“By virtue of its technical characteristics the project would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (2011/92/EU, amended 2014/52/EU), where the national authorities…”
supportsConsentConsent granted
Auction results1
[17]
RBINS / MUMM (Brabant, Degraer & Rumes, 2011 — Offshore wind farms in the Belgian part of the North Sea, ch. 2)2011◆ rbins-mumm-2011-belgian-owf-ch2
Table 1, "Overview of the dates when the projects were granted a domain concession and an environmental permit": C-Power 27/06/03 · Belwind 5/6/2007 · Eldepasco 15/5/2006 · Norther 5/10/2009 · Rentel …
supportsConcession · Belgian offshore wind zone — domain concessions (Thornton Bank–Bligh Bank)
Trade press3
[2]
Power Technology2020
Press report — cited, not quoted; read it at the source link.
supportsFoundationStatusConnection pointWater depthCoordinates
[5]
Windtech International2019-03-01◆ Windtech International - Norther offshor…
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionFirst power
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed