Arcadis Ost 1

Located 19km northeast of Rugen Island. Connected to 50Hertz Ostwind 2 system.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2013’14’15’16’17’18’19’20’21’22’23’24’25’26View the sources for Consent appliedConsent applied 20 Dec 2012 ◆View the sources for Consent grantedConsent granted 9 Sep 2014 ◆BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1)BNetzA Offshore Wind Auction 2018 (transitional) Apr 2018 · auction recordView the source for Final investment decisionFinal investment decision Jun 2021 ◆View the source for Offshore constructionOffshore construction Jun 2022 ◆View the sources for First powerFirst power Jan 2023 ◆View the sources for Commercial operationCommercial operation Dec 2023 ◆BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) 2018-04 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDParkwind (Virya Energy / Colruyt Group) → Parkwind (JERA) — 100.0% · closed 2023-07 2023-03 CORPORATETODAYKNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) KNK Wind GmbH KNK Wind GmbH not among today’s recorded owners — no sale recordedParkwind Ost GmbH — 100% today · operator Parkwind Parkwind 100%BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Parkwind (Virya Energy / Colruyt Group) → Parkwind (JERA) — 100.0% · closed 2023-07
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023→2023-12 · 2 recorded revisions · slipped +0.5 yr (first announced 2023)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2023-12
Offshore construction2022-06 → 2023-12
Construction ports
PortPort of Rønne (Bornholm) ◆turbine pre assembly
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationArcadis Ost 1 offshore substation·220 (export) kV · in service 2022 · owner Parkwind (wind farm developer) with 50Hertz Transmission — reported as jointly operated by Parkwind and the TSO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20222023202420252026developer’s stated start 2023-Q4nowArcadis Ost 1 offshore substationArcadis Ost 1 offshore substationin service 2022in service 2022

Sources & verification

Rests on 15 sources (11 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[13]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Arcadis Ost I": 27 units, 257.175 MW gross, statuses {'In Betrieb': 27}, operators ['Parkwind Ost'], commissioned 2023-01-20..2023-11-26, planned None..None.”
supportsRegister entry
Operator10
[1]
Staatliches Amt für Landwirtschaft und Umwelt Vorpommern (StALU VP)2021-03-31◆ Genehmigung nach § 16 BImSchG Offshore-W…
“Stralsund, 31.03.2021 Genehmigung Nr. 1.6.1G-60.022/19-50 gemäß § 16 Bundes-Immissionsschutzgesetz – BImSchG i. V. m. Nummer 1.6.1 Anhang 1 der Verordnung über genehmigungsbedürftige Anlagen - 4. BImS…”
supportsoperatorConsentModelUnit capacityFoundation+3 more
[2]
Parkwind2021-06-15◆ JERA Nex bp - Parkwind | Arcadis Ost 1 r…
“Arcadis Ost 1 reaches financial close on global wind day published on 15/06/2021 [...] Parkwind has the pleasure of announcing that the 257MW Arcadis Ost 1 offshore wind farm reached financial close .…”
supportsFinal investment decisionTurbinesModelUnit capacityTotal capacity
[3]
Parkwind2022-11-24
“The first out of the 27 Vestas V174 – 9.5MW turbines has successfully been installed [...] on November 24th 2022 [...] The installation campaign has started in June 2022 [...] using a unique floating …”
supportsOffshore constructionTurbinesModelUnit capacity
[4]
Parkwind2023-01-17
“The first Arcadis Ost 1 turbines have been successfully energized, and are now producing energy. It is the first wind farm equipped with Vestas V174-9.5MW turbines and Parkwind's first international p…”
supportsFirst powerModelUnit capacity
[6]
Parkwind / JERA Nex bp Parkwind2024-12
“257 MW [...] 27 turbines [...] inaugurated on December 5th 2023 [...] 19 km off Rügen Island in the federal state of Mecklenburg-Western Pomerania [...] Parkwind used a floating turbine installation m…”
supportsCommercial operationTurbinesTotal capacityDistance from shoreCoordinates
[7]
Vattenfall2021-07-29◆ Vattenfall takes on direct marketing for…
“Vattenfall will be marketing the Arcadis Ost 1 offshore windfarm [...] operators of newly installed renewable generation in Germany are obliged to sell the electricity they produce directly on the mar…”
supportsMechanismDetail
[8]
50Hertz2024◆ 50hertz.com > Grid > Grid developement >…
“Ostwind 2 is the project to connect the Baltic Sea wind farms Arcadis Ost 1 and Baltic Eagle to the German extra-high voltage transmission grid [...] The connection to the German extra-high voltage tr…”
supportsStatusConnection point
[14]
Unternehmensregister2024-12-31◆ Parkwind Ost GmbH, Sassnitz - Jahresabsc…
“Die garantierte Mindestvergütung für den Offshore Windpark Arcadis Ost 1 liegt bei 6,24 €ct/kWh. [...] Die Umsatzerlöse betragen zum 31. Dezember 2024 EUR 71.914.091,00 (Vorjahr: EUR 51.705.526,13) un…”
supportsMechanismDetail
[15]
IfAÖ for Parkwind Ost GmbH (application document in the StALU Vorpommern procedure, UVP-Verbund M-V)2019-09-18◆ Beschreibung des Änderungsgegenstandes f…
“20.12.2012 KNK Wind beantragt die Errichtung von 58 Windenergieanlagen, einer Umspann- plattform und die parkinterne Verkabelung gemäß § 4 Abs. 1 ... 09.09.2014 Baugenehmigung gemäß BImSchG durch das …”
supportsConsentConsent appliedConsent granted
[16]
Parkwind2023-07-26◆ JERA Nex bp Parkwind | Acquisition of Pa…
“JERA Co., Inc. successfully closed its acquisition of 100% of the shares of Parkwind NV from Virya Energy [...] Starting as of today, Parkwind will operate as part of JERA Co., Inc.”
supports↳ parent
Trade press4
[5]
offshoreWIND.biz2023-12-05◆ Parkwind's Arcadis Ost 1 Offshore Wind F…
Press report — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operationCOD historyTurbinesModel
[9]
offshoreWIND.biz2020-01-08
Press report — cited, not quoted; read it at the source link.
supportsturbine pre assembly
[11]
GEBCO Compilation Group2020
supportsWater depth
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed