Butendiek

Located 32km west of Sylt island.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2003’04’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26BSH Genehmigungsbescheid N-5.2, 18 Dec 2002 — 'Auf den Antrag der Offshore-Bürger-Windpark Butendiek GmbH & Co. KG … werden Errichtung und Betrieb von 80 einzelnen Windenergieanlagen … genehmigt.' The citizens' SPV (today OWP Butendiek GmbH & Co. KG under wpd) held the site at origination.Party of record at origination Dec 2002 · auction recordView the source for Consent grantedConsent granted 18 Dec 2002 ◆View the source for Final investment decisionFinal investment decision Feb 2013 ◆View the source for Offshore constructionOffshore construction Apr 2014 ◆View the source for First powerFirst power Feb 2015 ◆View the source for Commercial operationCommercial operation 2015-Q3 ◆BSH Genehmigungsbescheid N-5.2, 18 Dec 2002 — 'Auf den Antrag der Offshore-Bürger-Windpark Butendiek GmbH & Co. KG … werden Errichtung und Betrieb von 80 einzelnen Windenergieanlagen … genehmigt.' The citizens' SPV (today OWP Butendiek GmbH & Co. KG under wpd) held the site at origination. 2002-12 ORIGINATIONOffshore-Bürger-Windpark Butendiek GmbH & Co. KG → Airtricity — stake not disclosed 2007-04 ACQUISITIONAirtricity → SSE Renewables — stake not disclosed 2008 CORPORATESSE Renewables → wpd — 100% · closed 2010-09 2010-09-20 ACQUISITIONwpd → Marguerite Fund / Siemens Financial Services / Industriens Pension / PKA — 90.0% 2013-02 FARMDOWNMarguerite Fund → CDC Infrastructure — 7.5% 2013-12 wpd → ewz — 4.9% 2014-01 JV ENTRYPKA → ITOCHU / CITIC Pacific — 22.5% · closed 2017-03 2016-12 ewz → Octopus Energy Generation — 5.0% · closed 2023 2023-11 Marguerite Pantheon → Greencoat Renewables — 22.5% · €190m · closed 2023-02 2023-01 Transfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDSiemens Pension Trust → Greencoat Renewables — 22.5% · €168m · closed 2023-12 2023-10 Transfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYOffshore-Bürger-Windpark Butendiek GmbH & Co. KG Offshore-Bürger-Windpar… Offshore-Bürger-Windpar… not among today’s recorded owners — no sale recordedAirtricity Airtricity Airtricity exited 2008SSE Renewables SSE Renewables SSE Renewables exited 2010-09-20wpd wpd wpd exited 2014-01Marguerite Pantheon Marguerite Fund Marguerite Fund exited 2023-01Siemens Financial Services Siemens Financial Servi… Siemens Financial Servi… exited 2013-02Industriens Pension Industriens Pension Industriens Pension exited 2013-02PKA PKA PKA exited 2016-12CDC Infrastructure CDC Infrastructure CDC Infrastructure exited 2013-12ewz ewz ewz exited 2023-11ITOCHU ITOCHU ITOCHU exited 2016-12CITIC Pacific CITIC Pacific CITIC Pacific exited 2016-12Octopus Energy Generation Octopus Energy Generati… Octopus Energy Generati… exited 2023-11Greencoat Renewables Greencoat Renewables Greencoat Renewables exited 2023-10Siemens Pension Trust Siemens Pension Trust Siemens Pension Trust exited 2023-10OWP Butendiek GmbH & Co. KG — 100% today · operator OWP Butendiek GmbH & Co… OWP Butendiek GmbH & Co… 100%BSH Genehmigungsbescheid N-5.2, 18 Dec 2002 — 'Auf den Antrag der Offshore-Bürger-Windpark Butendiek GmbH & Co. KG … werden Errichtung und Betrieb von 80 einzelnen Windenergieanlagen … genehmigt.' The citizens' SPV (today OWP Butendiek GmbH & Co. KG under wpd) held the site at origination. Offshore-Bürger-Windpark Butendiek GmbH & Co. KG → Airtricity — stake not disclosed Airtricity → SSE Renewables — stake not disclosed SSE Renewables → wpd — 100% · closed 2010-09 100%wpd → Marguerite Fund / Siemens Financial Services / Industriens Pension / PKA — 90.0% wpd → Marguerite Fund / Siemens Financial Services / Industriens Pension / PKA — 90.0% wpd → Marguerite Fund / Siemens Financial Services / Industriens Pension / PKA — 90.0% wpd → Marguerite Fund / Siemens Financial Services / Industriens Pension / PKA — 90.0% 90% → consortiumMarguerite Fund → CDC Infrastructure — 7.5% 7.5%wpd → ewz — 4.9% 4.9%PKA → ITOCHU / CITIC Pacific — 22.5% · closed 2017-03 PKA → ITOCHU / CITIC Pacific — 22.5% · closed 2017-03 22.5% → consortiumewz → Octopus Energy Generation — 5.0% · closed 2023 5%Marguerite Pantheon → Greencoat Renewables — 22.5% · €190m · closed 2023-02 22.5%Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Siemens Pension Trust → Greencoat Renewables — 22.5% · €168m · closed 2023-12 22.5%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2015-Q3→2015-Q3 · 2 recorded revisions · held (announced 2015-Q3, unchanged)

Revenue & offtake the regime the project was built under

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2015-Q3
Offshore construction2014-04 → 2015-Q3
Construction ports
PortEsbjerg ◆·installation · quay 10000 m · crane 300 t · draft 15 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationUmspannwerk Butendiek·33/155 kV · owner OWP Butendiek GmbH & Co. KG (wind farm owner) — farm-owned, not TSO-owned
HVDC systemSylWin1·864 MW · ±320 kV · in service 2015-04 · shared with DanTysk, Sandbank
Converter supplierSiemens·SylWin1 · Nordic Yards (Warnowwerft, Rostock) · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2014201520162017201820192020202120222023202420252026developer’s stated start 2015-Q3nowSylWin1SylWin1first planned 2014first planned 2014in service 2015-04in service 2015-04

Sources & verification

Rests on 12 sources (20 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2002-12-18◆ Genehmigungsbescheid Offshore-Windpark B…
“Hamburg, den 18. Dezember 2002 Genehmigungsbescheid Auf den Antrag der Offshore-Bürger-Windpark Butendi ek GmbH & Co. KG [...] werden Errichtung und Betrieb von 80 einzelnen Windenergieanlagen (WEA) n…”
supportsoperatorConsentTurbinesCoordinatesConsent granted
[17]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Butendiek": 80 units, 288.0 MW gross, statuses {'In Betrieb': 80}, operators ['OWP Butendiek GmbH & Co. KG'], commissioned 2015-02-04..2015-08-03, planned None..None.”
supportsRegister entry
Operator7
[2]
OWP Butendiek GmbH & Co. KG2025
“288 MW wind farm [...] 80 Siemens wind turbines, having a rated power of 3.6 MW [...] in the North Sea, about 32 km west of the island of Sylt [...] convenient water depth of 20 m”
supportsUnit capacityTotal capacityDistance from shore
[3]
OWP Butendiek GmbH & Co. KG2025
“80 wind turbines by Siemens Wind Power [...] SWT-3.6-120 [...] Components are manufactured in Denmark and will be shipped from the port of Esbjerg”
supportsTurbinesModel
[4]
OWP Butendiek GmbH & Co. KG2025
“18 December 2002: Granting of approval – Butendiek is the second project in Germany being approved. February 2013: Financial close including debt financing [total investment volume is approx. € 1.3 bn…”
supportsFinal investment decision
[5]
wpd AG2015-08-04◆ Full power at Butendiek offshore wind fa…
"04. Aug 2015 – Full power at Butendiek offshore wind farm [...] Bringing the 80th and thus final wind turbine into operation, the construction of the offshore wind farm Butendiek is now complete." ..…
supportsCommercial operationCOD history
[13]
Ballast Nedam2014
"first monopile was installed on the 1st of April 2014 [...] the 80th and last monopile was installed on the 22nd of July 2014 [...] 32 km West of the German Island Sylt [...] between 17 and 22 metres…
supportsOffshore constructionSite rightsFoundationWater depthDistance from shore+1 more
[14]
OWP Butendiek GmbH & Co. KG2025
“The grid connection of the Butendiek wind farm is part of Tennet's Sylwin cluster which has the capacity of 864 MW and connects three wind farms west of Sylt. [...] Butendiek's offshore substation is …”
supportsStatusConnection point
[22]
Unternehmensregister2026-02-27◆ OWP Butendiek GmbH & Co. KG, Bremen - Ja…
“Die OWP Butendiek GmbH & Co. KG (im Folgenden kurz: Gesellschaft) hat ihren Sitz in Bremen. Das zuständige Registergericht ist das Amtsgericht Bremen, HRA 25927 HB. [...] Die Direktvermarktung erfolgt…”
supportsMechanismDetail
Financier1
[23]
Greencoat Renewables PLC2023-10-02◆ Further 22.5% investment in Butendiek of…
“an agreement to acquire an additional 22.5% stake in the Butendiek offshore wind farm ("Butendiek") from an affiliate of Siemens Pension Trust. [...] Greencoat Renewables expects to make the acquisiti…”
supports↳ parents
Trade press2
[15]
offshoreWIND.biz2015-02-05
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed