75 km2 area. Three-legged steel jacket foundations. Jackets assembled at Port of Brest.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2012’13’14’15’16’17’18’19’20’21’22’23’24’25’26France Offshore Wind Round 1 (AO1) — awarded to Ailes Marines (Iberdrola)France Offshore Wind Round 1 (AO1) Apr 2012 · auction recordView the source for Consent grantedConsent granted Jun 2018 ◆View the source for Final investment decisionFinal investment decision May 2020 ◆View the source for Offshore constructionOffshore construction May 2021 ◇View the source for First powerFirst power Jul 2023 ◆View the source for Commercial operationCommercial operation May 2024 ◆France Offshore Wind Round 1 (AO1) — awarded to Ailes Marines (Iberdrola) 2012-04 ORIGINATIONAvel Vor (RES Group / Banque des Territoires) → Iberdrola — 30.0% 2020-03 ACQUISITIONTODAYIberdrola — 100% today Iberdrola Iberdrola 100%Avel Vor (RES Group / Banque des Territoires) Avel Vor Avel Vor exited 2020-03France Offshore Wind Round 1 (AO1) — awarded to Ailes Marines (Iberdrola) Avel Vor (RES Group / Banque des Territoires) → Iberdrola — 30.0% 30%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023→2023→2024-05 · 3 recorded revisions · slipped +0.9 yr (first announced 2023)

Revenue & offtake contract duration and price levels · money of the day

496 MW contracted — tender award
● Tender award · France Offshore Wind Round 1 (AO1)
Price€155/MWh ·Capacity496 MWAwardedApr 2012
Term20 yrs

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2024-05
Offshore construction2021-05 → 2024-05
Construction ports
PortPort of Brest ◆·assembly · quay 400 m · crane 200 t · draft 10.6 m
PortPort of Lézardrieux ◆crew transfer
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationSaint-Brieuc Offshore Substation·225 kV · in service 2022 · owner Ailes Marines (100% Iberdrola Group) — the producer, NOT RTE
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20222023202420252026developer’s stated start 2024-Q2nowSaint-Brieuc Offshore SubstationSaint-Brieuc Offshore Substationin service 2022in service 2022

Sources & verification

Rests on 16 sources (7 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[2]
Iberdrola2024-05-28
supportsCOD history
[14]
Iberdrola2024◆ Iberdrola increases offshore wind ambiti…
“NI (2020-03-09) Iberdrola acquires 30% of Saint-Brieuc from RES and Caisse de Depots ... Avel Vor (RES and Caisse des Depots) sells its 30% equity in the EUR 2.4 billion investment project, scheduled …”
supportsowner
[18]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 855 (node--type-project) at /facades-maritimes-en-france/facade-nord-atlantique-manche-ouest/saint-brieuc — title 'Saint-Brieuc'; page text 1968 chars, hash 76669635fb992693…. Identifyin…”
supportsRegister entry
Auction results1
[24]
Commission de régulation de l'énergie / DGEC (published by the CPDP Courseulles)2026-10-13◆ fr-ao1-cahier-des-charges-full
Full AO1 cahier des charges (appel d'offres n. 2011/S 126-208873). 6.9: by T0 + 24 months the winner gives the prefect the draft authorisation applications; valid applications filed by T0 + 30 months;…
supportsTender award · France Offshore Wind Round 1 (AO1)
Trade press12
[1]
offshoreWIND.biz2024-05-28
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationTurbinesModelUnit capacityTotal capacity+4 more
[3]
offshoreWIND.biz2023-07-06
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[5]
offshoreWIND.biz2021-04-21
Press report — cited, not quoted; read it at the source link.
supportsassemblycrew transfer
[6]
offshoreWIND.biz2020-06-18
Press report — cited, not quoted; read it at the source link.
supportsFoundationassembly
[7]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacityDistance from shore
[8]
Energies de la Mer2021-01-29
“AO 01 … premier appel d'offres lancé en 2011 … ministerial decree of April 6, 2012 designating Ailes Marines as the winner … 62 turbines of 8 MW each … total power of 496 Megawatts … Ailes Marines (Ib…”
supportsMechanismDetail
[10]
Renewables Now2020-05-29◆ SGRE locks order for 496-MW Saint-Brieuc…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[11]
Energies de la Mer2018-06-25
“Parc de Saint-Brieuc : le nouvel arrêt a été signé … Prefect of Côtes-d'Armor signed a new decree on June 21, 2018, regularizing the initial decree … the April 18, 2017 decree approving the convention…”
supportsConsentConsent granted
[13]
The Wind Power2026-05◆ Saint-Brieuc (France) - Wind farms - Onl…
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[15]
GEBCO Compilation Group2020
supportsWater depth
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[23]
L'Info Durable (AFP)2021-08-06◆ Eolien en mer: retard dans les travaux d…
Copyrighted source — cited, not quoted; read it at the source link.
supportsOffshore construction