Windanker

Iberdrola's third offshore wind farm in German Baltic Sea. Japanese utility Kansai acquired 49% stake December 2024. Project valued at EUR 1.28 billion.

Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
WGWindanker GmbH — 100% ◆
Location
Germany
Baltic Sea
Technology
Capacity 315 MW ◆ Turbines 21 × 15 MW ◆ Model Siemens Gamesa SG 14-236 DD ◆ Foundation Monopile ◆
Site & conditions
Site rights Seabed rights held ∴
Origination BNetzA Offshore Wind Auction 2021 (central model) · 2021 ·
Water depth 41–46 m ◆ Distance from shore 38 km ◆ Wind speed 10.0 m/s @ 150 m ≈
Revenue & grid
Offtake PPA ◆ Grid Secured ◆ Connection 50Hertz Ostwind 3: Jasmund offshore substation (OSS, installed … ◆
Schedule
FID Jun 2024 ◆ COD · announced 2027 ◆
COD · Hafrok 2027 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2027
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; technical complexity pulls a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2026: 1.3% (conditional on completion) 2027: 75.4% (conditional on completion) 2028: 21.7% (conditional on completion) 2029: 1.6% (conditional on completion)2026now202775%20282029 Developer-announced COD: 2027 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2027developer cod guidance2024-06-27: the developer guided 2026 — source [2] — click for it2024-062026 [2]2025-04 → 2025-11: the developer guided 2026-Q4 in 2 statements — sources [7] [16] — click for the sources2025-112026-Q4 · held since 2025-04 (×2) [7,16]2026-06-10: the developer guided 2027 — source [12] — click for it2026-062027 [12]
COD probability by year, conditional on completion
YearProbability
20261.3%
2027 (expected)75.4%
202821.7%
20291.6%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2024-06-272026
2025-11-032026-Q4 (held since 2025-04-24, 2 statements)
2026-06-102027
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2025. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2026 Q3; the faster quarter of similar projects would be done by 2025 Q4, the slower quarter not until 2027 Q3.
3
Result
Expected commercial operation 2027, likely range 2026–2028 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27Developer-announced COD: 2027 announced COD 2027BNetzA Offshore Wind Auction 2021 (central model) — awarded to RWE Renewables Offshore Development One GmbHBNetzA Offshore Wind Auction 2021 (central model) Sep 2021 · auction recordView the source for Consent appliedConsent applied 31 Aug 2022 ◆View the source for Final investment decisionFinal investment decision Jun 2024 ◆View the source for Consent grantedConsent granted Jan 2025 ◆View the source for Offshore constructionOffshore construction Oct 2025 ◆View the source for First powerFirst power Aug 2026 ◇Commercial operation 2027 ·Hafrok expectedBNetzA Offshore Wind Auction 2021 (central model) — awarded to RWE Renewables Offshore Development One GmbH 2021-09 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDIberdrola → Kansai Electric Power — 49.0% · €180m · closed 2025-04 2024-12 FARMDOWNTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYRWE Renewables Offshore Development One GmbH RWE Renewables Offshore… RWE Renewables Offshore… not among today’s recorded owners — no sale recordedIberdrola Iberdrola Iberdrola exited 2024-12Kansai Electric Power Kansai Electric Power Kansai Electric Power exited 2024-12Windanker GmbH — 100% today · operator Windanker GmbH Windanker GmbH 100%BNetzA Offshore Wind Auction 2021 (central model) — awarded to RWE Renewables Offshore Development One GmbH Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Iberdrola → Kansai Electric Power — 49.0% · €180m · closed 2025-04 49%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (13 Oct 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +1.0 yr (first announced 2026) · the full guidance history is in the delivery chart above

Revenue & offtake zero-bid award · bilateral offtake

Auction won at €0.00/MWh — no state price support
The award carries no state price support — revenue rests on bilaterally contracted offtake. Corporate PPA contracts are not yet recorded as structured data; the Revenue & offtake rows carry what the record's sources state.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation under way
Installation · on record
StageUnder Construction
Offshore constructionstarted 2025-10
Turbinesnot reportedshown when the developer reports a dated count
Commissioned21 of 21100% · as of 2026-10-13 · official register (Germany's Marktstammdatenregister) · commissioning follows installation, so at least this many turbines stand
Expected start of operation2027
Construction ports
PortMukran ◆·marshalling · draft 13.5 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationJasmund·owner 50Hertz Transmission
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
202520262027Hafrok expects the farm to start in 2027developer’s stated start 2027nowJasmundJasmundplatform installed 2025-12-17platform installed 2025-12-17

Sources & verification

Rests on 10 sources (8 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2025-01◆ Planfeststellungsbeschluss Offshore-Wind…
“Rostock, den 24.01.2025 Planfeststellungsbeschluss A. Verfügender Teil I. Feststellung des Plans [...] Der Planfeststellungsbeschluss umfasst 21 (Offshore-)Windenergieanlagen (im Folgend en: OWEA) sow…”
supportsoperatorConsentTurbinesModelUnit capacity+6 more
[17]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "OWP Windanker": 21 units, 315.0 MW gross, statuses {'In Planung': 21}, operators ['Windanker GmbH'], commissioned None..None, planned 2026-12-31..2026-12-31.”
supportsRegister entry
Operator1
[10]
50Hertz Transmission GmbH2026-02
“Ostwind 3 connects the Windanker wind farm [...] to Germany's grid. The system comprises approximately 100 kilometres of submarine cable and roughly 4.5 kilometres of underground onshore cable, both o…”
supportsStatusConnection point
Trade press7
[2]
offshoreWIND.biz2024-06-27◆ Iberdrola Greenlights Its Third Offshore…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionTotal capacity
[8]
offshoreWIND.biz2023-03-30
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetail
[12]
offshoreWIND.biz2026-06-10◆ Windanker Turbine Components Arriving at…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historymarshallingNorse Energi — turbine installation
[14]
offshoreWIND.biz2025-10-01
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionSvanen — foundation installation
[15]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[18]
offshoreWIND.biz2026-09-01◆ Iberdrola’s New German Offshore Wind Far…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[22]
offshoreWIND.biz2025-04-24◆ Iberdrola, Kansai Close EUR 1.28 Billion…
Press report — cited, not quoted; read it at the source link.
supports↳ parent