Hollandse Kust Noord

Located 18.5km off Egmond aan Zee. At least 3.3 TWh/year.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2019’20’21’22’23’24’25’26View the source for Consent appliedConsent applied 15 Jun 2018 ◆View the source for Consent grantedConsent granted 4 Apr 2019 ◆View the source for Final investment decisionFinal investment decision 2020 ◆Hollandse Kust (noord) Site V — awarded to CrossWind (Shell + Eneco)Hollandse Kust (noord) Site V Jul 2020 · auction recordView the source for Offshore constructionOffshore construction Oct 2022 ◆View the source for First powerFirst power 19 Jun 2023 ◆View the source for Commercial operationCommercial operation 20 Dec 2023 ◆Hollandse Kust (noord) Site V — awarded to CrossWind (Shell + Eneco) 2020-07 ORIGINATIONTODAYShell (via CrossWind C.V.) — 79.9% today · operator Shell Shell 79.9%Eneco (via CrossWind C.V.) — 20.1% today · partner Eneco Eneco 20.1%Hollandse Kust (noord) Site V — awarded to CrossWind (Shell + Eneco)
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023→2023-12-20 · 2 recorded revisions · slipped +0.5 yr (first announced 2023)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2023-12-20
Offshore construction2022-10 → 2023-12-20
Construction ports
PortBuss Terminal Eemshaven ◆·turbine marshalling · quay 5000 m · crane 50 t · draft 14 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationHollandse Kust (noord) Alpha·220 kV · in service 2023 · owner TenneT (Dutch TSO)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2023202420252026developer’s stated start 2023-Q4nowHollandse Kust (noord) AlphaHollandse Kust (noord) Alphain service 2023in service 2023

Sources & verification

Rests on 12 sources (10 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[2]
RVO2019-10◆ Hollandse Kust (noord) kavel V - Project…
“Project and Site Description Hollandse Kust (noord), Version October 2019. Appendix C: Boundaries and Coordinates HKNWFS.”
supportsWater depthDistance from shoreCoordinates
[3]
RVO2020-07◆ RVO Hollandse Kust Noord site V results
“On 29 July 2020, the Minister of Economic Affairs and Climate Policy announced the permits for Hollandse Kust (noord) Wind Farm Site V has been issued to CrossWind C.V., a consortium comprising Shell …”
supportsMechanismDetail
Operator4
[1]
Ministry of Economic Affairs and Climate Policy (Netherlands)2019-04-04◆ Kavelbesluit V windenergiegebied Holland…
“Kavel V windenergiegebied Hollandse Kust (noord) wordt aangewezen als locatie voor een windpark met een totaal geinstalleerd vermogen van minimaal 693 MW tot maximaal 760 MW. ... Kavel V in windenergi…”
supportsConsentTotal capacityFoundationStatusConnection point+5 more
[5]
Eneco2020-07-29◆ CrossWind wins tender for Hollandse Kust…
“On 29 July 2020, CrossWind C.V. - a joint venture between Shell in the Netherlands and Eneco - has won the tender for the Hollandse Kust (noord) offshore wind farm. Both companies have already taken t…”
supportsFinal investment decision
[6]
CrossWind / Eneco2023-06-19
“On June 19 the Hollandse Kust Noord offshore wind park produced its first megawatt-hours (MWh) of green energy, and delivered it via TenneT's offshore grid to the Dutch mainland.”
supportsFirst power
[11]
Eneco2023-12-20
“The consortium plans to have Hollandse Kust (noord) operational in 2023, with expected generation of at least 3.3 TWh per year. CrossWind is a joint venture between Shell in the Netherlands and Eneco.”
supportsBackground
OEM1
[4]
CrossWind / Siemens Gamesa2021-02-11
“CrossWind is a joint venture between Shell (79.9%) and Eneco (20.1%). The Notice to Proceed has been signed, following the issuance of the irrevocable permit from Dutch authorities in December 2020. T…”
supportsTurbinesModelUnit capacityTotal capacity
Trade press5
[7]
offshoreWIND.biz2022-10-18
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionFoundationDistance from shore
[8]
offshoreWIND.biz2023-12-20◆ Hollandse Kust Noord Offshore Wind Farm …
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historyTurbinesModelUnit capacity+1 more
[10]
WindpowerNL2021-09-23
Press report — cited, not quoted; read it at the source link.
supportsturbine marshalling
[13]
NS Energy2024
Press report — cited, not quoted; read it at the source link.
supportsoperatorpartner
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed