Netherlands
* maturity derived from capacity data; full assessment pending.
Assessment
This market has a derived snapshot above but no in-depth assessment yet. Authored coverage rolls out market by market; the data here is live in the meantime.
State of the market
as of 2026-10-13Delivered to 13 Oct 2026; expected from then. The 2026 column is 0.7 GW still expected this year, with nothing delivered so far: 1 farm with a stated completion of 2026 or earlier, 0.8 GW nominal, weighted and spread by its completion-date distribution. 19 GW of live pipeline weights to 12 GW expected to complete. Projects on hold, and projects with no dated milestone, are modelled and sit in the expected line.
Source: Hafrok · hafrok.com/markets/netherlands · data as of 13 Oct 2026
How this line is made
The Expected Buildout line answers one question: of the pipeline announced today, how much actually gets built, and when? It is not a scenario and not a target tracker; it is the database's live pipeline, passed through two filters measured from the industry's own delivery record.
Whether a project completes. Every project in development carries a completion weight, banded Delivering / Expected / Prospective / Fragile. A proposal (a site where no authority has yet granted rights) carries none and sits outside this line entirely; it is listed, not counted. The starting point is the historical completion rate of its lifecycle stage: of projects that reached construction, 97% delivered; financed but not yet building, 92%; consented without financing, 75%; early development, 61%; on hold, 15%. That base rate is then adjusted by what the project has actually secured (offtake, grid, consents, investment decision) and decays if a project sits quiet past its stage's normal dwell time.
When it delivers. Each project also carries a completion-date distribution: a shape, not a single year, right-skewed because offshore wind slips late far more often than it runs early. The peak sits on a rule-based expected date chained from the project's latest achieved milestone; the width of the late tail is fitted to how far past their announced dates real projects actually landed: builders slip tight (60% on time, n=144), financed projects tighter still (76%, n=95), consented-only projects carry the fat tail, with 21% landing three or more years late (n=126). A stated date faster than any comparable project has ever achieved is floored to the achievable window and flagged, never taken at face value.
The line is the sum, across every live project, of capacity × completion weight × the probability it delivers in each year. For projects already under construction, a share of expected capacity is counted at first power, because turbines start generating before a wind farm is fully commissioned, so a market's chart can show capacity arriving a year before a project's stated completion date. Delivered history is metered fact; the line inherits every assumption above and nothing else.
Honest limits. The weights are calibrated on a fleet whose failures have so far been overwhelmingly pre-financing, so completion rates after FID rest on a record with few failures and are ceilings, not guarantees. The slip fitted on consented projects is the loosest (the "three or more years late" bucket spans many years). Policy shocks arrive faster than base rates move; the weights see a stop-work order only as its lifecycle consequences accrue. And the line redistributes as the database learns: it is re-derived on every data refresh, not frozen.
Full per-project workings (each project's weight, band, expected date and distribution) are on its project page. Calibration v2.0-phase0 · generated 2026-10-13; every figure above is read from the generated calibration file, never typed.
Auction outlook
forecast · 4 rounds trackedThe single imminent Dutch item: permit applications open September 2026. SUBSIDY-backed (flip back from subsidy-free after the market weakened), price cap EUR 104/MWh, budget ~EUR 2.5bn. Not yet awarded.
Second 1 GW Gamma site; tender timing TBD (a later 2026 decision). Mechanism expected subsidy-backed like Gamma-A (not confirmed).
To be tendered together after Nederwiek I-A FAILED (zero applications, Oct 2025 — a settled null-result backfill, not a forecast). No firm tender year published; ~2027-2028 is inferred from the 5 GW infrastructure timing, not an explicit RVO date.
Later roadmap sites (Additional Offshore Wind Energy Roadmap) with NO published tender years — toward 2030+. Doordewind I/II ~2 GW each; HKW VIII ~700 MW; North of the Wadden Islands I ~700 MW. (Lagelander was dropped from the roadmap — excluded.)
Source: Hafrok · hafrok.com/markets/netherlands · data as of 13 Oct 2026
Origination ladder
settled rounds → projectsSource: Hafrok · hafrok.com/markets/netherlands · data as of 13 Oct 2026
10 sites designated for forecast rounds (13.4 GW) are not in the history ladder — pre-tender zones are the auction outlook's rounds-in-waiting: Doordewind I · Doordewind II · Hollandse Kust West Site VIII · IJmuiden Ver Gamma-A · IJmuiden Ver Gamma-B · Nederwiek I-A · Nederwiek I-B · Nederwiek II · Nederwiek III · Ten noorden van de Waddeneilanden I.