Rhyl Flats

Located 8km NE of Llandudno in Liverpool Bay, North Wales. Round 1 development.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2001’02’03’04’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 1 — awarded to RWECrown Estate Round 1 Apr 2001 · auction recordView the source for Consent grantedConsent granted 2002 ◆View the source for Offshore constructionOffshore construction Jul 2007 ◇View the source for Onshore constructionOnshore construction 2008 ◇View the source for First powerFirst power Jul 2009 ◇View the source for Commercial operationCommercial operation Dec 2009 ◇Crown Estate Round 1 — awarded to RWE 2001-04 ORIGINATIONRWE → Green Investment Group — 24.95% · €67m · closed 2013-Q1 2013-03 FARMDOWNRWE → Greencoat UK Wind — 24.95% · closed 2013-Q1 2013-02 FARMDOWNTODAYRWE — 50.1% today · operator RWE RWE 50.1%Green Investment Group — 24.95% today Green Investment Group Green Investment Group 24.95%Greencoat UK Wind — 24.95% today Greencoat UK Wind Greencoat UK Wind 24.95%Crown Estate Round 1 — awarded to RWE RWE → Green Investment Group — 24.95% · €67m · closed 2013-Q1 24.95%RWE → Greencoat UK Wind — 24.95% · closed 2013-Q1 24.95%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake the regime the project was built under

Offtake regime: ROC 1.5 ROCs/MWh
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2009-12
Offshore construction2007-07 → 2009-12
Construction ports
PortPort of Mostyn ◆construction

Sources & verification

Rests on 10 sources (8 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[14]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2495: Site Name "Rhyl Flats", Development Status "Operational", Installed Capacity 90 MWelec, Operator "RWE Npower"”
supportsRegister entry
Operator2
[1]
RWE2025◆ Rhyl Flats offshore wind farm
“Rhyl Flats is a 90 megawatt wind farm, consisting of 25 turbines located approximately 8 kilometres north east of Llandudno in North Wales. The wind farm is owned by a consortium of RWE (50.1%), Green…”
supportsoperatorownerTurbinesTotal capacityDistance from shore
[2]
Green Investment Group (formerly UK Green Investment Bank)2013-03-22◆ First direct equity investment in offsho…
“The UK Green Investment Bank (GIB) has acquired a 24.95% stake in Rhyl Flats Wind Farm Limited from companies owned by RWE AG for a cash consideration of £57.5m in its first direct equity investment i…”
supportsWater depth
Trade press6
[4]
Pacific Northwest National Laboratory (Tethys)2026◆ Rhyl Flats | Tethys
"Rhyl Flats is operated by RWE and is owned by a consortium of RWE (50.1%), Green Investment Group (24.95%) and Greencoat (24.95%)." "2002: Celtic Offshore Wind Limited (COWL) received full consents"
supportsConsentFoundationConsent granted
[5]
Renewable Energy Foundation2024
“offshore wind farms accredited prior to 1 April 2007 receive 1 ROC per MWh, between 1 April 2007 and 1 April 2010, 1.5 ROCs per MWh and after 1 April 2010 are awarded two ROCs per MWh.”
supportsMechanismDetail
[9]
Daily Post (North Wales Live)2008-08-06
“Workers at the Port of Mostyn completed the first phase of the Rhyl Flats offshore windfarm, which saw foundation piles and transition pieces installed in the seabed off Rhyl using the heavy lift vess…”
supportsconstruction
[10]
Daily Post (North Wales Live)2009-04-08
“Work on the onshore electrical substation at Towyn is nearing completion.”
supportsStatusConnection point
[12]
Global Energy Monitor2026-07-02
supportsCoordinates
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[3]
Wikipedia2026
“The first electricity was supplied by the site on 15 July 2009. The completed project was officially opened on 2 December 2009. Offshore construction work at Rhyl Flats began in July 2007.”
supportsFinal investment decisionOnshore constructionOffshore constructionFirst powerCommercial operation+3 more