Ormonde

Located in East Irish Sea off Barrow-in-Furness. Four-legged steel jacket foundations.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2001’02’03’04’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 1 — awarded to (Eclipse Energy; built by Vattenfall)Crown Estate Round 1 Apr 2001 · auction recordView the source for Consent grantedConsent granted 4 Sep 2008 ◆View the source for Onshore constructionOnshore construction Nov 2009 ◆View the source for Offshore constructionOffshore construction May 2010 ◆View the source for First powerFirst power Aug 2011 ◆View the source for Commercial operationCommercial operation Feb 2012 ◆Crown Estate Round 1 — awarded to (Eclipse Energy; built by Vattenfall) 2001-04 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDVattenfall → AMF (Swedish pension fund) — 49% · €325m · closed 2016-Q1 2015-12 FARMDOWNTODAY(Eclipse Energy; built by Vattenfall) not among today’s recorded owners — no sale recordedVattenfall — 51% today · operator Vattenfall Vattenfall 51%AMF — 49% today · investor AMF AMF 49%Crown Estate Round 1 — awarded to (Eclipse Energy; built by Vattenfall) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Vattenfall → AMF (Swedish pension fund) — 49% · €325m · closed 2016-Q1 49%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2012-Q1→2012-02 · 2 recorded revisions · held within the year (first announced 2012-Q1, latest 2012-02)

Revenue & offtake the regime the project was built under

Offtake regime: ROC 2.0 ROCs/MWh
RegimeROC 2.0 ROCs/MWh
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2012-02
Offshore construction2010-05 → 2012-02
Construction ports
PortBarrow-in-Furness ◆
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationOrmonde Offshore Substation Platform (OSP)·owner Transmission Capital Partners (TCP) — acquired the Ormonde transmission assets as OFTO, with the OSP inside the transfer perimeter. BUILT for and originally owned by Vattenfall AB, through Ormonde Energy Limited. The party named on the record today is not the builder.

Sources & verification

Rests on 13 sources (13 primary) · ◆ 10 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[5]
Ofgem2009-07◆ Ormonde Offshore Transmission — Project-…
“The Ormonde Wind Farm is to be located 10 km off Walney Island in the East Irish Sea. A single subsea cable will connect the OSP to the mainland, with the onshore connection point being at the Trimpel…”
supportsStatusConnection pointDistance from shoreport
[15]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2509: Site Name "Ormonde Offshore", Development Status "Operational", Installed Capacity 150 MWelec, Operator "Vattenfall"”
supportsRegister entry
Operator5
[1]
Vattenfall AB2012-09-19◆ Offshore windpark Ormonde officieel in g…
“Vattenfall's offshore windpark Ormonde (150 MW), wordt vandaag officieel in gebruik genomen. Het is het eerste commerciële windpark met windmolens van 5 MW. Het windpark ligt voor de kust van Cumbria …”
supportsTurbinesUnit capacityTotal capacity
[2]
Vattenfall AB2011-08-19◆ Brits windpark Ormonde produceert eerste…
“Gisterenavond om 20.00 uur produceerde windpark Ormonde voor het eerst elektriciteit. [...] Ormonde ligt op tien kilometer voor de kust in de Ierse Zee. [...] De bouw van het park startte vorig jaar m…”
supportsFirst powerDistance from shore
[4]
Vattenfall AB2011-03-24◆ Eerste turbine op Vattenfall’s Ormonde o…
“Vattenfall is begonnen met de installatie van één van 's werelds grootste offshore windturbines voor het Engelse offshore windpark Ormonde. De 153 meter hoge turbine van 5 Megawatt (mw) met een gewich…”
supportsTurbinesModelUnit capacityTotal capacity
[11]
Vattenfall2025
“In 2015, Vattenfall entered a partnership with Swedish pension group AMF. The partnership agreement means that AMF own a 49% share and Vattenfall continues to operate the wind farm as the majority sha…”
supportsoperatorinvestor
[16]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000216: "Ormonde Offshore Wind Farm", Status "Built", MW Connected 150, Effective From n/a, Customer "ORMONDE ENERGY LIMITED"”
supportsRegister entry
Trade press5
[6]
Tethys (PNNL) — abstract of Vattenfall/Ormonde Energy Ltd 2010 CEMR2010◆ Ormonde Offshore Wind Farm 2010 Construc…
"The Ormonde Offshore Wind Farm is a 150MW project located approximately 10km west of Walney Island, Barrow in Furness, Cumbria, in roughly 20 metres of water. It comprises up to 30 turbines at 5MW ea…
supportsConsentFoundationConsent granted
[7]
offshoreWIND.biz2012-02-22◆ Vattenfall Completes Ormonde Offshore Wi…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionCommercial operationCOD history
[8]
offshoreWIND.biz2012-09-19◆ UK: Ormonde Offshore Wind Farm Officiall…
Press report — cited, not quoted; read it at the source link.
supportsModelFoundation
[10]
Power Technology (GlobalData)2023◆ Ormonde Offshore Wind Farm - Power Techn…
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[12]
Wikipedia2026-07-02
supportsCoordinates