Nordergrunde
Located 15km NE of Wangerooge island in German North Sea 12nm zone.
Technology
Capacity
111 MW ◆
Turbines
18 × 6.2 MW ◆
Model
Senvion 6 2m126 ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Water depth
6–10 m ≈
Distance from shore
16 km ◆
Wind speed
9.5 m/s @ 100 m ≈
Revenue & grid
Offtake
Premium ◆
Grid
Secured · Oct 2017 ◆
Connection
TenneT AC 155kV; 32km cable (28km subsea + 4km onshore) to … ◆
Schedule
FID
Jun 2015 ◆
COD
Dec 2017 ◆
Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (13 Oct 2026).
Announced-COD history: 2017-Q4→2017-12 · 2 recorded revisions · held within the year (first announced 2017-Q4, latest 2017-12)
Revenue & offtake the regime the project was built under
Offtake regime on record
RegimeThe farm company's accounts state that it sells its power by direct marketing under the EEG through a direct marketer (contract concluded in 2015; a new contract with Danske Commodities from 1 Jan 2022), under the compressed tariff model (Stauchungsmodell) with a reference value of 19.4 ct/kWh. In 2022 market values in some months were above 19.4 ct/kWh and raised the farm's revenue. The accounts held (FY2019, FY2021, FY2022) do not say how long the 19.4 ct/kWh rate runs or what rate follows.
Instrumentmarket premium
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from sourced statements and Hafrok’s registers
Installation complete
Installation · on record
StageOperational
In operation since2017-12
Offshore construction2016-08 → 2017-12
Construction ports
PortBremerhaven (Eurogate Container Terminal) ◆·installation · quay 4930 m · draft 12.8 m
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationNordergründe offshore substation·owner wpd AG's project company at construction; Skyborn Renewables took full ownership of the wind farm (own-2026-07-de-nordergrunde). The platform sits inside the wind farm's scope, not TenneT's — see builder_basis.
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
Rests on 14 sources (12 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[15]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "OWP Nordergründe": 18 units, 110.7 MW gross, statuses {'In Betrieb': 18}, operators ['OWP Nordergründe GmbH & Co. KG'], commissioned 2017-11-03..2017-12-17, planned None..None.”
supportsRegister entry
Operator3
[9]
Skyborn Renewables2026
“Nordergründe [...] 111 MW [...] Commissioned in 2017 [...] 18 Senvion turbines [...] Located 13 kilometres off Lower Saxony's coast [...] supplies renewable energy to approximately 110,000 households.”
supportsTurbinesModelTotal capacity
[13]
wpd AG2016-08-19
“After the successful assembly of all 18 foundation structures, conversion of the installation ship, the MPI Enterprise, for erecting the wind turbines in the Weser estuary began at the beginning of Au…”
supportsOffshore constructionSite rights
[16]
Unternehmensregister2024-03-07◆ OWP Nordergründe GmbH & Co. KG, Bremen -…
“Die OWP Nordergründe GmbH & Co. KG (im Folgenden kurz: Gesellschaft) hat ihren Sitz in Bremen. Das zuständige Registergericht ist das Amtsgericht Bremen, HRA 26977 HB. [...] Da Nordergründe bereits in…”
supportsMechanismDetail
Financier1
[2]
European Investment Bank2015-06-02◆ Germany: EIB supports Nordergründe offsh…
“The European Investment Bank (EIB) is lending EUR 156m for the Nordergründe wind farm, which is one of the first offshore wind farm projects developed in Germany. Located in the German coastal part of…”
supportsTurbinesTotal capacityDistance from shore
Trade press9
[1]
Presseportal / Energiekontor AG2007-11-19◆ Genehmigung für den Offshore-Windpark No…
“19.11.2007 – 16:48 EnergieKontor AG Genehmigung für den Offshore-Windpark Nordergründe erteilt Bremen (ots) Vom Gewerbeaufsichtsamt in Oldenburg - der für die Genehmigung verantwortlichen Verfahrensfü…”
supportsConsentConsent granted
[3]
offshoreWIND.biz2017-11-02◆ Nordergründe OWF Finally Running | Offsh…
Press report — cited, not quoted; read it at the source link.
supportsFirst powerStatusConnection point
[4]
offshoreWIND.biz2017-12-18◆ Last Nordergründe Turbine Hooked to the …
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historyTurbinesModelUnit capacity+1 more
[5]
offshoreWIND.biz2016-08-19
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[6]
Power Technology2018
Press report — cited, not quoted; read it at the source link.
supportsFoundationCoordinates
[7]
offshoreWIND.biz2016-03-10
Press report — cited, not quoted; read it at the source link.
supportsinstallation
[11]
[12]
[14]