Borssele 1 & 2

Located 22 km off the coast of Zeeland, Netherlands. Connected via the TenneT Borssele Alpha offshore substation (66 kV to 220 kV export).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2016’17’18’19’20’21’22’23’24’25’26View the source for Consent appliedConsent applied 7 Aug 2015 ◆View the source for Consent grantedConsent granted 24 Mar 2016 ◆Borssele Wind Farm Sites I & II — awarded to Ørsted Borssele 1 B.V. (then DONG Energy)Borssele Wind Farm Sites I & II Jul 2016 · auction recordFinal investment decision 2018 ∅View the source for Offshore constructionOffshore construction Jan 2020 ◆View the source for First powerFirst power Apr 2020 ◆View the sources for Commercial operationCommercial operation Dec 2020 ◆Borssele Wind Farm Sites I & II — awarded to Ørsted Borssele 1 B.V. (then DONG Energy) 2016-07 ORIGINATIONØrsted → NBIM — 50% · €1,375m · closed 2021-05 2021-04 FARMDOWNTODAYØrsted — 50% today · operator Ørsted Ørsted 50%Norges Bank Investment Management (NBIM) — 50% today · investor NBIM NBIM 50%Borssele Wind Farm Sites I & II — awarded to Ørsted Borssele 1 B.V. (then DONG Energy) Ørsted → NBIM — 50% · €1,375m · closed 2021-05 50%
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2020→2020→2020-12 · 3 recorded revisions · slipped +0.5 yr (first announced 2020)

Revenue & offtake contract duration and price levels · money of the day

752 MW contracted — tender award
● Tender award · Borssele Wind Farm Sites I & II
Price€72.7/MWh ·Capacity752 MWAwardedJul 2016
Term15 yrs

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2020-12
Offshore construction2020-01 → 2020-12
Construction ports
PortVlissingen Buitenhaven (O&M base) ◆·operations · quay 1740 m · crane 1200 t
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationBorssele Alpha·66/220 kV · in service 2020 · owner TenneT (Dutch TSO — client of the EPCIC contract)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2020202120222023202420252026developer’s stated start 2020-Q4nowBorssele AlphaBorssele Alphain service 2020in service 2020

Sources & verification

Rests on 14 sources (7 primary) · ◆ 13 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[2]
RVO (Netherlands Enterprise Agency)2015-09◆ Borssele Wind Farm Zone Sites I and II -…
“The BWFZ … is located 22.2 km from shore (12 nautical miles) and will be sub-divided into four BWFS. Water depth is approximately 16-38 m.”
supportsStatusConnection pointDistance from shore
[3]
RVO (Netherlands Enterprise Agency)2016-07-05◆ RVO Borssele I & II results
“On 5 July 2016 the subsidy and permits for the Borssele Wind Farm Sites I and II were awarded to Ørsted Borssele 1 B.V. … With 94 turbines type Siemens Gamesa 8,0 MW-167 DD this wind farm will get a t…”
supportsTurbinesModelUnit capacityTotal capacityMechanism+1 more
Operator5
[1]
Ministerie van Economische Zaken (Netherlands)2016-03-24◆ Kavelbesluit I windenergiegebied Borssel…
“'s-Gravenhage, 24 maart 2016 — De Minister van Economische Zaken, H.G.J. Kamp”
supportsConsentConsent appliedConsent granted
[4]
Ørsted A/S2017-07◆ Orsted signs agreement with Siemens Game…
“Ørsted has signed a contract with Siemens Gamesa for its Borssele 1 and 2 offshore wind farm in the Netherlands. ... The wind farm will be located 22km off the coast of the Dutch province of Zeeland w…”
supportsTurbinesModelUnit capacityTotal capacityWater depth+2 more
[5]
Ørsted A/S2017-08◆ Orsted chooses Vlissingen Buitenhaven fo…
“Ørsted and Zeeland Seaports have signed a Letter of Intent for developing an O&M base in Vlissingen Buitenhaven for the operation and maintenance of the offshore wind farm Borssele 1&2.”
supportsoperations
[6]
Ørsted A/S2021-02◆ Ørsted Annual Report 2020
“In December, we commissioned the 752 MW Dutch wind farm Borssele 1 & 2 on schedule and within budget. The wind farm deploys 94 Siemens Gamesa 8 MW wind turbines, making it the largest-ever built in th…”
supportsCommercial operationCOD history
[7]
Ørsted A/S2022-02◆ Ørsted Annual Report 2021
“Norges Bank Investment Management (NBIM) became a 50 % shareholder in our 752 MW Borssele 1 & 2 project. The total value of the transaction amounted to DKK ~10.2 billion and marks NBIM's first investm…”
supportsoperator
Auction results1
[14]
Overheid.nl (wetten.overheid.nl)2015◆ nl-regeling-borssele-1-2
Regeling windenergie op zee 2015 — the tender rulebook (rung-2 allocation regulation) for Borssele I & II. SDE+ subsidised round; text references the award of "subsidies" under the SDE+ scheme. Auctio…
supportsTender award · Borssele Wind Farm Sites I & II
Trade press6
[8]
offshoreWIND.biz2020-04-29◆ Borssele 1 & 2 Generates First Power | O…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[9]
offshoreWIND.biz2020-11-27◆ Borssele 1&2 Fully Commissioned | Offsho…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[10]
offshoreWIND.biz2021-05-31◆ Ørsted Divests Half of Borssele 1 & 2 OW…
Press report — cited, not quoted; read it at the source link.
supportsinvestor
[11]
WindpowerNL2020-01-13◆ Start foundation construction at Borssel…
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionFoundation
[12]
offshoreWIND.biz2016-07-05◆ DONG Energy Winner of Dutch Borssele I &…
Press report — cited, not quoted; read it at the source link.
supportsMechanismStrike / priceDetail
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed