Hornsea Two
Located 89km off Yorkshire coast. 1320 MW grid connection capacity (165 x 8 MW turbines).
Status
Operationallifecycle stage
Ownership
Location
North Sea
Technology
Capacity
1,320 MW ◆
Turbines
165 × 8.4 MW ◆
Model
Siemens Gamesa SG 8-0-167 DD ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 3 · 2010 ·
Water depth
25–67 m ◆
Distance from shore
89 km ◆
Wind speed
10.0 m/s @ 100 m ≈
Revenue & grid
Offtake
CfD · AR2 ◆
Grid
Connected ◆
Connection
Grid connection secured. North Killingholme 400kV substation. … ◆
Schedule
FID
2017 ◆
COD
2022-Q3 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2010-01
Crown Estate Round 3
- Awarded to
- SMart Wind (Mainstream Renewable Power + Siemens Project Ventures)
- Zone
- Hornsea zone
- Basis
- seabed award
From the auction results — the round that created the project.
Farmdown · 2022-03
Ørsted → AXA IM Alts / Credit Agricole Assurances 50%
- Stake
- 50%
- Consideration
- €3,366m
- Implied 100% value
- €6,731m
- Implied
- €5.10m / MW
- Basis
- Price for the equity
- Announced
- 2022-03
- Closed
- 2022-09
- Project stage
- operational
Ørsted sold 50% of Hornsea Two (Hornsea Two Holdings Limited, owner of the three farm companies) to a consortium of AXA IM Alts and Crédit Agricole Assurances, through Juno BidCo Limited. Signed 28 March 2022 while the farm was being built; completed on 29 September 2022 once it was commissioned. Ørsted put the total value of the transaction at GBP 3bn; the buyer's audited accounts record GBP 1,179.8m for 50% of the shares and GBP 1,635.1m of shareholder loans taken over, GBP 2,814.9m in all. The buyers financed their purchase partly with bank loans in their own company. The export cables were sold to the OFTO in 2023. EUR figure at the ECB 2022-03 monthly average.
Evidence
- Ørsted — Ørsted partners with AXA IM Alts and Crédit Agricole Assurances on Hornsea 2 Offshore Wind Farm ↗ 2022-03-28 ◆ held
- offshoreWIND.biz — Ørsted Divesting Half of Hornsea Two for EUR 3.6 Billion ↗ 2023-02 ◆ held
- Ørsted — Orsted completes divestment of 50 % of Hornsea 2 Offshore Wind Farm ↗ 2022-09-29 ◆ held
- Companies House — Breesea Limited - full accounts to 31 December 2021 ↗ 2022-10-07 ◆ held
- Companies House — Sonningmay Wind Limited - full accounts to 31 December 2021 ↗ 2022-10-07 ◆ held
- Companies House — Soundmark Wind Limited - full accounts to 31 December 2021 ↗ 2022-10-07 ◆ held
- Companies House — Optimus Wind Limited - full accounts to 31 December 2021 ↗ 2022-09-28 ◆ held
- Ørsted — Agreement on the sale of Hornsea 2 transmission assets ↗ 2023-07-21 ◆ held
- Companies House — Juno BidCo Limited - group accounts to 31 December 2022 ↗ ◆ held
From Hafrok’s transactions record
Farmdown · 2024-10
Ørsted → Brookfield 12.45%
- Stake
- 12.45%
- Consideration
- not disclosed
- Announced
- 2024-10
- Closed
- 2024-12
- Project stage
- operational
Hornsea 2 was the world's largest operational offshore wind farm at commissioning. See Hornsea 1 record for full transaction context and CRITIC NOTE on deal value allocation. Combined portfolio = Hornsea 1 (1,218 MW) + Hornsea 2 (1,320 MW) + Walney Extension (659 MW) + Burbo Bank Extension (258 MW) = 3,455 MW combined. All four assets are CfD-contracted and fully operational. Ørsted retains 37.55%. Data confidence: HIGH.
Evidence
- Ørsted A/S — Orsted divests share of four UK offshore wind farms to Brookfield ↗ 2024-10 ◆ held
- bep.brookfield.com — Brookfield Acquires Share of Four UK Offshore Wind Farms from Ørsted ↗ 2024-10 ◆ held
- Ørsted A/S — Ørsted completes divestment of share of four UK offshore wind farms ↗ 2024-12 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023→2022→2022→2022-08-31 · 4 recorded revisions · pulled forward -0.8 yr (first announced 2023)
Revenue & offtake contract duration and price levels · money of the day
CfD-backed offtake
● CfD · AR2
Price£57.5/MWh ·Basis2012 real · CPI-indexed
Capacity1,386 MWAwardedSep 2017Term15 yrs · delivery 2022/23
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-08, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR2
Installation how the build is going · from sourced statements and Hafrok’s registers
Installation complete
Installation · on record
StageOperational
In operation since2022-Q3
Offshore construction2020-10 → 2022-Q3
Installation contracts
Offshore substationSleipnir◇Heerema · heavy-lift vessel · 2021 → 2021-10 · CompletedGrid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationHornsea Two offshore substation (OSS)·66/220 kV · owner Diamond Transmission Partners Hornsea Two (OFTO); built by Ørsted
Offshore substationHornsea Two Reactive Compensation Station·owner Diamond Transmission Partners Hornsea Two (OFTO); built by Ørsted
Sources & verification
Rests on 13 sources (17 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[2]
UK Department for Business, Energy & Industrial Strategy / National Grid2017-09-11◆ CfD Allocation Round 2 results
“Hornsea Project 2 Breesea Limited Offshore Wind 1,3 86.00 57.50 2022/23 2 1,440,300 England ... 2 Hornsea will be built in three phases; 2022/23 is the delivery year for phase 1”
supportsMechanismDetail
[14]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2502: Site Name "Hornsea 2 - Optimus and Breesea", Development Status "Operational", Installed Capacity 1320 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
[23]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010053: "Hornsea Offshore Wind Farm (Zone 4) - Project Two"; applicant "SMart Wind Limited"; Stage "Post-decision"; applied 2015-01-30; accepted 2015-02-19; decision 2016-08-16.”
supportsConsentConsent appliedConsent granted
Operator3
[1]
Ørsted (Decommissioning Programme filed under the Energy Act 2004)◆ Hornsea Project Two Offshore Wind Farm D…
"Onshore construction works commenced in April 2018, works in the intertidal area commenced in April 2019, and offshore construction is due to commence in 2020 with commissioning in 2022." ... Hornsea…
supportsConsentOnshore constructionOffshore constructionTurbinesModel+9 more
[3]
Ørsted2022-08-31◆ Hornsea 2, the world’s largest windfarm,…
“Ørsted is proud to announce that the world's largest installed windfarm, Hornsea 2, is now fully operational.”
supportsCommercial operationCOD historyTotal capacity
[15]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000333: "Hornsea Power Station 2A", Status "Built", MW Connected 440, Effective From n/a, Customer "BREESEA LIMITED"; PRO-000334: "Hornsea Power Station 2…”
supportsRegister entry
Auction results1
[24]
BEIS (gov.uk)2017-09◆ cfd-ar2-results-2017
Triton Knoll Offshore Wind Farm — Offshore Wind 860.00 MW, GBP 74.75, 2021/22; Hornsea Project 2 (Breesea Limited) — 1,386.00 MW, GBP 57.50, 2022/23; Moray Offshore Windfarm (East) — 950.00 MW, GBP 57…
supportsCfD · AR2
Record source1
[25]
offshore-energy.biz / offshoreWIND.biz2021-10-27◆ oe-hornsea-two-substations-2021-10
Press report — cited, not quoted; read it at the source link.
supportsSleipnir — substation installation
Trade press5
[4]
CNBC2021-12-21◆ Orsted: Milestone for wind farm expected…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
offshoreWIND.biz2024-10
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[9]
offshoreWIND.biz2017-09-11
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[10]
offshoreWIND.biz2020-10-09
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[11]