East Anglia ONE

Located in the southern North Sea off Suffolk coast. 714 MW grid connection.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall)Crown Estate Round 3 Jan 2010 · auction recordView the source for Consent grantedConsent granted 17 Jun 2014 ◆View the source for Final investment decisionFinal investment decision 24 Feb 2016 ◆View the source for Onshore constructionOnshore construction 2017 ◆View the source for Offshore constructionOffshore construction Jun 2018 ◆View the source for First powerFirst power Sep 2019 ◆View the source for Commercial operationCommercial operation 2020-Q3 ◆Crown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDScottishPower Renewables (Iberdrola) → Green Investment Group (Macquarie) — 40% · €1,311m · closed 2019-09 2019-08 FARMDOWNGreen Investment Group (Macquarie) → TRIG (14.3%) / InfraRed EIIF4 (5.7%) — 20% · closed 2021-03 2020-11 Macquarie Asset Management → L&G NTR Clean Power (Europe) Fund / Development Bank of Japan — 10% 2024-05 Macquarie Asset Management → Octopus Energy Generation (Vector fund) — 10% 2025-04 Transfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYEast Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) East Anglia Offshore Wi… East Anglia Offshore Wi… not among today’s recorded owners — no sale recordedScottishPower Renewables — 60% today · operator ScottishPower Renewables ScottishPower Renewables 60%Green Investment Group (Macquarie) Green Investment Group Green Investment Group exited 2020-11The Renewables Infrastructure Group — 14.3% today TRIG TRIG 14.3%InfraRed EIIF4 (5.7%) InfraRed EIIF4 InfraRed EIIF4 exited 2020-11Macquarie Asset Management Macquarie Asset Managem… Macquarie Asset Managem… exited 2025-04L&G NTR Clean Power Fund — 5% today L&G NTR Clean Power Fund L&G NTR Clean Power Fund 5%Development Bank of Japan — 5% today Development Bank of Jap… Development Bank of Jap… 5%Octopus Energy Generation — 10% today Octopus Energy Generati… Octopus Energy Generati… 10%InfraRed Capital Partners (IREIIF4) — 5.7% today InfraRed Capital Partne… InfraRed Capital Partne… 5.7%Crown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed. ScottishPower Renewables (Iberdrola) → Green Investment Group (Macquarie) — 40% · €1,311m · closed 2019-09 40%Green Investment Group (Macquarie) → TRIG (14.3%) / InfraRed EIIF4 (5.7%) — 20% · closed 2021-03 Green Investment Group (Macquarie) → TRIG (14.3%) / InfraRed EIIF4 (5.7%) — 20% · closed 2021-03 20% → consortiumMacquarie Asset Management → L&G NTR Clean Power (Europe) Fund / Development Bank of Japan — 10% Macquarie Asset Management → L&G NTR Clean Power (Europe) Fund / Development Bank of Japan — 10% 10% → consortiumMacquarie Asset Management → Octopus Energy Generation (Vector fund) — 10% 10%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (13 Oct 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2018→2020-07 · 2 recorded revisions · slipped +2.0 yr (first announced 2018)

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
● CfD · AR1
Price£119.89/MWh ·
Basis2012 real · CPI-indexed
Capacity714 MWAwardedFeb 2015
Term15 yrs · delivery 2017/18
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-08, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR1
50100150200nowCfD · AR1 — £119.89/MWh · 2012 real · CPI-indexedCfD · AR1 — £119.89/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR1 term · 15 yrs2015201820212024202720302033CfD · AR1 — £119.89/MWh · 2012 real · CPI-indexed — 124.8 at award177.0 now

Installation how the build is going · from sourced statements and Hafrok’s registers

Installation complete
Installation · on record
StageOperational
In operation since2020-Q3
Offshore construction2018-06 → 2020-Q3
Construction ports
PortPeel Ports Great Yarmouth ◆construction
PortPort of Lowestoft (ABP Hamilton Dock) ◆operations and maintenance
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationAndalucia II offshore substation·66/220 kV · owner ScottishPower Renewables; OFTO transfer to TC East Anglia One OFTO Ltd expected Q3 2022 (completion unconfirmed in fetched sources)

Sources & verification

Rests on 18 sources (11 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Planning Inspectorate2014-06-17◆ East Anglia ONE Offshore Windfarm - Proj…
“Application EN010025 - post-decision stage, application granted. 17 June 2014: the Secretary of State for Energy and Climate Change issued the East Anglia ONE offshore wind farm order. 43km from the S…”
supportsConsentDistance from shoreConsent granted
[2]
DECC2015-02◆ CfD Allocation Round 1 results (Official…
“East Anglia ONE CfD Allocation Round 1, strike price GBP 119.89/MWh (2012 prices). ... DECC has today 26 February 2015 at 7AM published the outcome of the first allocation round ... EA 1 | Scottishpow…”
supportsMechanismStrike / priceDetailCfD · AR1
[21]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2524: Site Name "East Anglia 1 (EA 1)", Development Status "Operational", Installed Capacity 714 MWelec, Operator "Scottish Power Renewables"”
supportsRegister entry
Operator3
[20]
Green Investment Group (Macquarie)2020-07-27◆ East Anglia reaches major milestone with…
“All 102 turbines, situated 43km off the Suffolk coast, are now fully operational and have the capacity to produce 714 MW of clean power, enough to power the equivalent of more than 630,000 homes.”
supportsCOD history
[22]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000268: "East Anglia One", Status "Built", MW Connected 680, Effective From n/a, Customer "EAST ANGLIA ONE LIMITED"”
supportsRegister entry
[23]
Iberdrola2026-02-24◆ Iberdrola — gsm26 annual accounts consol…
“the recognition in 2025 of the insurance compensation for the East Anglia One cable failure that occurred in 2024”
supportsStatus note
Trade press12
[3]
Offshore Wind Biz2016-02-24
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[4]
NS Energy Business
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[6]
Offshore Wind Biz2019-09-12
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
Offshore Wind Biz2016-03-02
Press report — cited, not quoted; read it at the source link.
supportsconstruction
[9]
Offshore Wind Biz2019-10-18
Press report — cited, not quoted; read it at the source link.
supportsoperations and maintenance
[13]
Transmission Investment
“Onshore Grid Connection Point: Bramford. The 220kV export route is 85km offshore and 37km onshore and comes ashore close to the village of Bawdsey. A single 220/66kV offshore substation steps up the v…”
supportsStatusConnection point
[14]
Power Technology
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacityFoundationDistance from shore
[15]
Offshore Wind Biz2021-09-27
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationModel
[16]
offshoreWIND.biz2025-04
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[17]
4C Offshore (TGS)2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[18]
GEBCO Compilation Group2020
supportsWater depth
[19]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed