Dogger Bank A
Phase A of the 3.6 GW Dogger Bank complex (A+B+C) — when complete, the world's largest offshore wind farm.
Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
Location
North Sea
Technology
Capacity
1,200 MW ◇
Turbines
95 × 13 MW ◇
Model
GE Haliade X 13 MW ◇
Foundation
Monopile ◇
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 3 · 2010 ·
Water depth
16–31 m ≈
Distance from shore
131 km ◇
Wind speed
10.4 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · AR3 ◆
Grid
Partial ◇
Connection
HVDC connection to Creyke Beck 400kV substation ◇
Schedule
FID
2020 ◆
COD · announced
2026 ◆
COD · Hafrok
2026 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2026
expected year of commercial operation
Chance of delivery
≈98%
estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
| Year | Probability |
|---|---|
| 2025 | 1.3% |
| 2026 (expected) | 75.4% |
| 2027 | 21.7% |
| 2028 | 1.6% |
| Stated | Announced COD |
|---|---|
| 2020-11-26 | 2024 |
| 2024-10-03 | 2025 (held since 2024-05-22, 2 statements) |
| 2026-05-28 | 2026 (held since 2026-02-04, 2 statements) |
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in
2020. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2021 Q3; the faster quarter of similar projects would be done by 2020 Q4, the slower quarter not until 2022 Q3. Dates already in the past are moved up to today — this project has run beyond the typical timing.3
Result
Expected commercial operation
2026, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it
Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2010-01
Crown Estate Round 3
- Awarded to
- Forewind (SSE, RWE Npower, Statoil, Statkraft)
- Zone
- Dogger Bank zone
- Basis
- seabed award
From the auction results — the round that created the project.
Farmdown · 2020-12
SSE Renewables / Equinor → Eni 20%
- Stake
- 20%
- Consideration
- €223m
- Implied 100% value
- €1,117m
- Implied
- €0.93m / MW
- Basis
- Price for the equity
- Announced
- 2020-12
- Closed
- 2021-02
- Project stage
- FID
Eni acquired 20% of Dogger Bank A and B in a single transaction (10% from each of SSE and Equinor). Combined consideration GBP 405m for both phases; per-phase value ~GBP 202.5m. Financial close reached 25 Nov 2020. Eni's stake later transferred to Vårgrønn (Plenitude/HitecVision JV) in Oct 2022. EUR figure at the ECB 2020-12 monthly average (1.1035 EUR per GBP).
Evidence
- doggerbank.com — Dogger Bank Wind Farm announces Eni as new partner for phases A and B ↗ 2020-12 ◆ held
From Hafrok’s transactions record
Corporate · 2022-06
Eni Plenitude → Vårgrønn (Plenitude / HitecVision JV) 20%
- Stake
- 20%
- Consideration
- not disclosed
- Announced
- 2022-06
- Closed
- 2022-10
- Project stage
- under construction
Intra-group restructuring — not an arm's-length transaction. Plenitude transferred its 20% stake in all three Dogger Bank phases (A/B/C, 3,600 MW combined) to Vårgrønn (65% Plenitude / 35% HitecVision JV). HitecVision increased its Vårgrønn ownership from 30.4% to 35%. See Dogger Bank B and C companion records.
Evidence
- Dogger Bank Wind Farm JV — Vargronn acquires Plenitude's 20% interest in Dogger Bank Wind Farm ↗ 2022-10 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (13 Oct 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +2.0 yr (first announced 2024) · the full guidance history is in the delivery chart above
Revenue & offtake contract duration and price levels · money of the day
CfD-backed offtake
● CfD · AR3
Price£39.65/MWh ·Basis2012 real · CPI-indexed
Capacity1,200 MWAwardedSep 2019Term15 yrs · delivery 2023/24
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-08, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR3
Installation how the build is going · from sourced statements and Hafrok’s registers
Installation under way
Installation · on record
StageUnder Construction
Offshore constructionstarted 2022-07
Turbines95 of 95◆100% · as of 2026-10-05 · reported by Dogger Bank Wind FarmExpected start of operation2026
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemDogger Bank A HVDC·1200 MW · ±320 kV · in service 2023-10
Export & onshore
Export cableDogger Bank A Export Cable·HVDC subsea · 207 km · NKT · to Beverley, East Riding of Yorkshire
Converter supplierHitachi Energy·Dogger Bank A HVDC · Aibel (Haugesund, Norway) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
Rests on 18 sources (16 primary) · ◆ 11 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator5
[6]
UK Department for Business, Energy & Industrial Strategy2019-10-11◆ CfD Allocation Round 3 results
“Creyke Beck A P1 (Dogger Bank A) — 1,200 MW at £39.650/MWh (2012 prices).”
supportsMechanismDetail
[7]
UK Statutory Instrument 2015/318 (Planning Inspectorate EN010021)2015-02-17◆ The Dogger Bank Creyke Beck Offshore Win…
“The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 You are here: UK Statutory Instruments 2015 No. 318 ... 3. Development consent, etc. granted by Order”
supportsConsentCoordinatesConsent appliedConsent granted
[19]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2541: Site Name "Dogger Bank A & B (was Creyke Beck A & B)", Development Status "Under Construction", Installed Capacity 2400 MWelec, Operator "SSE/Equinor (for…”
supportsRegister entry
[24]
legislation.gov.uk2015-02-17◆ The Dogger Bank Creyke Beck Offshore Win…
“The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 Made 17th February 2015 Coming into force 11th March 2015 ... Bizco 1 is granted— (a) development consent for the Project A offshore works, th…”
supportsConsentConsent appliedConsent granted
[25]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010021: "Dogger Bank Creyke Beck"; applicant "Forewind Limited"; Stage "Post-decision"; applied 2013-08-29; accepted 2013-09-25; decision 2015-02-17.”
supportsConsentConsent appliedConsent granted
Operator7
[2]
[3]
Equinor2023-10-10◆ World’s largest offshore wind farm Dogge…
“Dogger Bank started producing first power on 10 October 2023. ... 10 October 2023 06:00 ( UTC ) ... The first turbine at Dogger Bank A has started turning and producing electricity. Power from the off…”
supportsFirst powerVoltaire — turbine installation
[11]
Equinor2020-11-26◆ Equinor and partner reach financial clos…
“Dogger Bank wind farm owners, Equinor and SSE, have today announced financial close on the first two phases of the project, representing in aggregate the largest offshore wind project financing to dat…”
supportsFinal investment decision
[12]
SSE Renewables2020-01-17◆ Construction commences for Dogger Bank |…
“Construction on the world’s largest offshore wind farm has taken place this week near the coastal village of Ulrome, East Riding of Yorkshire, England. ... Jones Bros Civil Engineering ... has been aw…”
supportsOnshore constructionOffshore construction
[15]
SSE plc2026-05-28
“Following the completion of turbine installation at Dogger Bank A in February 2026, commissioning continues and is expected to be substantially complete by the end of calendar year 2026.”
supportsCommercial operationCOD history
[20]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000411: "Dogger Bank Project A", Status "Built", MW Connected 1200, Effective From n/a, Customer "DOGGERBANK OFFSHORE WIND FARM PROJECT 1 PROJCO LIMITED"”
supportsRegister entry
[21]
SSE plc2026-07-16◆ SSE Renewables — sse plc q1 fy27 trading…
“Commissioning work continues on Dogger Bank A in line with expectations.”
supportsCommercial operation
Auction results1
[26]
BEIS (gov.uk)2019-09◆ cfd-ar3-results-2019
Offshore Wind awards (2012 prices): Doggerbank Creyke Beck A P1 1,200.00 MW, GBP 39.650, 2023/24; Creyke Beck B P1 1,200.00 MW, GBP 41.611, 2024/25; Teeside A P1 1,200.00 MW, GBP 41.611, 2024/25; Sofi…
supportsCfD · AR3
Trade press5
[4]
offshoreWIND.biz2026-02-23
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[5]
offshoreWIND.biz2025-11-27
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacityFoundation
[13]
Dogger Bank Wind Farm2025
“It is a joint venture partnership between SSE Renewables (40%), Equinor (40%) and Vårgrønn (20%).”
supportsoperatorowner
[14]
[16]